Great Lakes Water Authority Logo
File #: 2018-1065    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/21/2018 In control: Board of Directors
On agenda: 1/23/2019 Final action: 1/23/2019
Title: Proposed Change Order No. 1 Contract No. GLWA-CON-280 Relocation of the Industrial Waste Control Division to the GLWA Water Resource Recovery Facility (WRRF) Contractor/Vendor: Tooles Contracting Group, LLC
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Title
Proposed Change Order No. 1
Contract No. GLWA-CON-280
Relocation of the Industrial Waste Control Division to the GLWA Water Resource Recovery Facility (WRRF)
Contractor/Vendor: Tooles Contracting Group, LLC

Body
Agenda of January 23, 2019
Item No: 2018-1065
Amount:

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority

DATE: December 21, 2018

RE: Proposed Change Order No. 1
Contract No. GLWA-CON-280
Relocation of the Industrial Waste Control Division to the GLWA Water Resource Recovery Facility (WRRF)
Contractor/Vendor: Tooles Contracting Group, LLC

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operations, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA) authorizes the Chief Executive Officer (CEO) to grant an increase of 90 calendar days to final completion time for Contract No. GLWA-CON-280 "Relocation of the Industrial Waste Control Division", Tooles Construction Group LLC (Contractor) and also authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND

GLWA Contract CON-280 was awarded to Tooles Contracting Group LLC for a total price of $1,653, 600.00 on May 23, 2018. The Contract Substantial Completion Date is December 22, 2018 and the Contract Final Completion Date is January 21, 2019.
The purpose of the project is to relocate the Industrial Waste Control Division (IWCD) from its current location on Livernois Avenue to the WRRF. The project includes the following scope of work:

Sampler Prep Area - First Floor of the WRRF Administration Building
Demolition of existing locker and toilet room elements, roof replacement, and construction of a new work area for sampler cleaning and maintenance (including new sinks, counters, ice maker, and sample refrigerator).

General Offices - First Floor of the...

Click here for full text