Title: Contract No. 1804129 Schoolcraft Road 48 Inch Water Transmission Main CIP# 122005 / BCE 42.0
Sponsors: Cheryl Porter, Grant Gartrell
Indexes: Water Operations
Attachments: 1. 1804129 Procurement Report, 2. 1804129 Cost Summary, 3. 1804129 CIP Attachment
Title
Contract No. 1804129
Schoolcraft Road 48 Inch Water Transmission Main
CIP# 122005 / BCE 42.0
Body
Agenda of: October 31, 2019
Item No.: 2019-362
Amount: $14,490,960.20

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority

DATE: October 2, 2019

RE: Contract No. 1804129
Schoolcraft Road 48 Inch Water Transmission Main
Vendor: Lakeshore Global


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1804129 "Schoolcraft Road 48 Inch Water Transmission Main" with Lakeshore Global, at a cost not to exceed $14,490,960.20 for a duration of 730 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
Contract No. 1804129 is a construction contract that involves constructing approximately 2.1 miles of new 48-inch diameter steel water transmission main along westbound Schoolcraft Road. This new main will replace an existing 48-inch diameter prestressed concrete embedded cylinder pipe (PCCP) located along eastbound Schoolcraft Road. This existing main is part of an older system with a history of catastrophic breaks. A portion of the new 48-inch diameter main was installed in the Interstate 96 (I-96) freeway when it was reconstructed in 2015 under the Michigan Department of Transportation (MDOT) Contract No. 82188-89095.
JUSTIFICATION
The existing 48-inch PCCP transmission main along this segment of Schoolcraft Road has had a history of breaks. The manufacturer of this transmission main segment has a documented history of failures due to hydrogen embrittlement of its prestressed steel wires. Replacing this existing PCCP water transmission main will improve water service reliability in GLWA's system.
FINANCIA...

Click here for full text