File #: 2021-216    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/1/2021 In control: Board of Directors
On agenda: 6/23/2021 Final action: 6/23/2021
Title: Contract No. 2004456 14 Mile Road Transmission Loop - Phase II CIP# 122013 / BCE Score: 58.4
Sponsors: Cheryl Porter, Grant Gartrell
Indexes: Water Operations
Attachments: 1. 2004456 Procurement Report, 2. 2004456 Cost Tabulation, 3. 2004456 CIP Attachment

Title

Contract No. 2004456

14 Mile Road Transmission Loop - Phase II

CIP# 122013 / BCE Score: 58.4

Body

Agenda of:                     June 23, 2021

Item No.:                     2021-216

Amount:                     $92,468,705.00

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     June 2, 2021

 

RE:                                          Contract No. 2004456

                                          14 Mile Road Transmission Loop - Phase II

                                          Vendor:  Ric-Man/Clark JV (Joint Venture)

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2004456
“14 Mile Transmission Main Loop - Phase II” with Ric-Man/Clark JV, at a cost not to exceed $92,468,705.00 for a duration of 845 days;
and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

Several of GLWA’s member partners, including West Bloomfield Township, Farmington Hills, Commerce Township, Novi, Walled Lake, and Wixom are currently served drinking water through a single feed transmission main. As a result, any major breaks on this transmission main will cause loss of water service to the people, health care facilities, schools, and businesses in these communities. Therefore, the purpose of this project is to construct new transmission main and isolation valves in a looped configuration to eliminate this single feed condition that currently exists in this area of GLWA’s water system. Construction of the 14 Mile Road Water Transmission System Loop is being done in two phases. Phase I is currently under construction and involves constructing approximately 1 mile of 24-inch diameter transmission main, associated gate valves, blow-offs and air valves and additional tie-ins to master meters WA-01, NV-04 and CM-01. Phase II of this project is this proposed construction contract, which will complete the loop and provide the necessary redundancy in this area of GLWA’s water system. This construction contract will involve constructing approximately 42,000 feet of 54-inch diameter pipe, isolation valves, a pipeline cathodic protection system, and pipeline appurtenances. The new pipeline will run generally along the I-275 corridor from 8 Mile Road to 11 Mile Road, then along the Meadowbrook Road right-of-way to 13 Mile Road, and finally along the M-5 corridor to GLWA’s Haggerty Pump Station at 14 Mile and Haggerty Roads.

JUSTIFICATION

Constructing the new water transmission main and appurtenances under this construction contract will complete the 14 Mile Transmission System looping project and eliminate the single feed condition that currently exists in this area of GLWA’s water system.

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: Water Construction Fund

Cost Center: Water Field Engineering

Expense Type: Construction (5519-882411.000-616900-122013)

Estimated Cost by Year and Related Estimating Variance:  See table below.

 

Fiscal Year

FY 2022 Plan                                                                                                         $35,126,000.00

FY 2023 Plan                                                                                                            35,126,000.00

FY 2024 Plan                                                                                                           20,691,000.00

Financial Plan Estimate                                                                                    $90,943,000.00

Proposed Contract Award                                                                                      92,468,705.00

Estimating Variance                                                                                                              ($  1,525,705.00)

This estimating variance to be funded from capital reserves.

SAVINGS, COST OPTIMIZATION, AND REVENUE ENHANCEMENT IMPACT

The cost savings are not determinable at the time of award.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on June 9, 2021.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.