File #: 2023-122    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/23/2023 In control: Board of Directors
On agenda: 4/26/2023 Final action: 4/26/2023
Title: Proposed Change Order No. 4 Contract No. 1803621 Wick Road 48-Inch Water Transmission Main CIP #122006 / BCE Score: 54.20
Sponsors: Cheryl Porter
Indexes: Water Operations
Title
Proposed Change Order No. 4
Contract No. 1803621
Wick Road 48-Inch Water Transmission Main
CIP #122006 / BCE Score: 54.20

Body
Agenda of: April 26, 2023
Item No.: 2023-122
Amount: Original Contract $20,962,361.00
Change Order No. 1 1,217,151.00
Change Order No. 2 549,032.40
Change Order No. 3 460,000.00
Proposed Change Order No. 4 250,000.00
Total Revised Contract $23,438,544.40

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: March 31, 2023

RE: Proposed Change Order No. 4
Contract No. 1803621
Wick Road 48-Inch Water Transmission Main
Vendor: Ric-Man Construction, Inc.


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1803621, Proposed Change Order No. 4, "Wick Road 48-Inch Water Transmission Main" with Ric-Man Construction, Inc., with an increased cost of $250,000.00 for a total cost not to exceed $23,438,544.40 and an increased duration of 365 days for a total duration of 1,754 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
GLWA Contract No. 1803621, Wick Road 48-inch Water Transmission Main, involves constructing approximately 17,000 linear feet of 48-inch diameter water transmission main parallel to an existing transmission main to provide redundancy between GLWA's Wick and Ypsilanti Booster Stations. To date, the contractor has installed roughly 16,500 linear feet of pipe, and remaining work includes the final interconnection and new valve installation near the Wick Booster Station.
Change Order No. 1 consisted of cost and time incurred due to CSX Transportation requirements regarding permeation grouting under the Wic...