Proposed Amendment No. 2
Contract No. 1904738/SCN-0000309
Job Order Contract - Instrumentation and Controls Maintenance Services (WRRF & CSOs)
O&M
Body
Agenda of: August 27, 2025
Item No.: 2025-253
Amount: Original Contract $7,620,000.00
Amendment No. 1 0.00
Proposed Amendment No. 2 0.00
Total Contract Amount $7,620,000.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority
DATE: August 4, 2025
RE: Contract No. 1904738/SCN-0000309
Job Order Contract - Instrumentation and Controls Maintenance Services (WRRF & CSOs)
Vendors: Outbound Technologies, Inc., PCI LLC, Rockwell Automation, UIS Scada Inc., CEC Controls Company Inc.
Status: Amendment/Change Order
MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1904738/SCN-0000309, Proposed Amendment No. 2, "Job Order Contract - Instrumentation and Controls Maintenance Services (WRRF & CSOs)" with Outbound Technologies, Inc., PCI LLC, Rockwell Automation, UIS Scada Inc., CEC Controls Company Inc. with no increase in cost for a total cost not to exceed $7,620,000.00, and an increased duration of 730 days for a total duration of 2,555 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
GLWA maintains and operates a large system of water treatment plants, water booster stations, transmission lines, the Water Resource Recovery Facility (WRRF), 11 Sewage Pumping Stations, a Regional Wastewater Collection System, nine CSO Facilities, and several other ancillary facilities t...