Title
Proposed Change Order No. 4
Contract No. PC-795 (SCN-0000480)
Pumping Station No. 2 Pumping Improvements
CIP #211002 / BCE Score: N/A
Body
Agenda of: February 26, 2025
Item No.: 2025-037
Amount: Original Contract $3,275,000.00
Change Order No. 1 (303,980.00)
Change Order No. 2 0.00
Change Order No. 3 0.00
Proposed Change Order No. 4 0.00
Total Contract Amount: $2,971,020.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority
DATE: January 27, 2025
RE: Contract No. PC-795 (SCN-0000480)
Pumping Station No. 2 Pumping Improvements
Vendor: Commercial Contracting Corporation
Status: Amendment/Change Order
MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. PC-795 (SCN-0000480), Proposed Change Order No. 4, Pumping Station No. 2 Pumping Improvements with Commercial Contracting Corporation, with no increase in cost for a total cost not to exceed $2,971,020.00 and an increased duration of 306 days for a duration of 3,362 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
On October 5, 2016, Tooles Contracting Group (Tooles) and GLWA entered into a contract for replacement and improvement of Pump No. 11 and 14 for Pump Station No. 2.
On January 19, 2021, Change Order No. 1 was executed, changing the Substantial Completion Date and the Final Completion Date for the entire project while accepting Pump No. 11 with a negotiated credit, based on the performance of the pump deviation from the agreement's specified performance criteria. Additionally, GLWA agreed to revise the performance criteria for Pump No. 14 to align with...