File #: 2024-314    Version: 1 Name:
Type: Resolution Status: New Business
File created: 9/24/2024 In control: Operations and Resources Committee
On agenda: 10/9/2024 Final action:
Title: Proposed Amendment No. 1 Contract No. 1903453 (SCN-0000219) Systems Control Center Support Services O&M
Sponsors: Cheryl Porter
Indexes: Water Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Proposed Amendment No. 1
Contract No. 1903453 (SCN-0000219)
Systems Control Center Support Services
O&M

Body
Agenda of: October 23, 2024
Item No.: 2024-314
Amount: Original Contract $2,028,000.00
Proposed Amendment No. 1 1,520,000.00
Total Contract Amount $3,548,000.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: September 27, 2024

RE: Proposed Amendment No. 1
Contract No. 1903453 (SCN-0000219)
Systems Control Center Support Services
Vendor: PCI, LLC


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1903453 (SCN-0000219), Proposed Amendment No. 1, "Systems Control Center Support Services" with PCI, LLC, at an increased cost of $1,520,000.00 for a total cost not to exceed $3,548,000.00 and an increased duration of 365 days for a total duration of 1,461 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.


BACKGROUND
This contract provides consultant's services which includes providing qualified personnel and performing related work to support the operations of equipment of the GLWA Systems Control Center group. The Operations Staffing Services contracts have successfully been utilized to assist the authority to respond to emergencies and to stay in compliance with state and federal regulations for water and wastewater systems. They also provide the necessary support for urgent and emergency situations that require immediate attention. GLWA's large service area and its 24/7 operation at any given time has only two team members to respond to the emergencies and support other day to day activities.
JUSTIFICATION
This work consists of providing wet weather/storm watch ...