Title
Proposed Change Order No. 2
Contract No. 2101878-1
Construction Agreement for the HAZMAT Building Rehabilitation
CIP #260901/BCE Score: 52.1
Body
Agenda of: June 26, 2024
Item No.: 2024-216
Amount: Original Contract $2,932,000.00
Change Order No. 1 0.00
Proposed Change Order No. 2 176,250.00
Revised Contract $3,108,250.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority
DATE: June 14, 2024
RE: Proposed Change Order No. 2
Contract No. 2101878-1
Construction Agreement for the HAZMAT Building Rehabilitation
Vendor: LaSalle Construction Services, Inc
Designer: Wade Trim
MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2101878-1, Proposed Change Order No. 2, "Construction Agreement for the HAZMAT Building Rehabilitation" with LaSalle Construction Services, Inc, at an increased cost of $176,250.00 for a total cost not to exceed $3,108,250.00 with no increase in duration for a total duration of 548 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
GLWA awarded LaSalle Construction Services, Inc. (Contractor) the construction agreement for the HAZMAT Building Rehabilitation. The purpose of this contract is to do a comprehensive renovation of the existing HAZMAT facility including the expansion of the equipment bay, building envelope upgrades, complete interior renovations, site upgrades, and the demolition of the guard shack. Change Order No. 1 revised the contract end date to November 27, 2024, and although work is progressing, there is additional work that the building department has required that requi...
Click here for full text