2026-140
| 1 | A. | | Minutes | March 11, 2026 Operations and Resources Committee Meeting Minutes (Draft) | | |
Not available
|
Not available
|
|
2026-139
| 1 | A. | | Communication | Receipt of Correspondence | | |
Not available
|
Not available
|
|
2026-124
| 1 | A. | | Resolution | Proposed Amendment No. 1
Contract No. 2002350/SCN-0000251
Preventative Maintenance and Repair of Rotork Actuators
O&M | | |
Not available
|
Not available
|
|
2026-138
| 1 | B. | | Resolution | Proposed Change Order No. 1
Requisition No. REQ-0007283/SCN-0000800
Emergency Construction Contract for Lake Huron Water Treatment Plant High Lift Building Column Repairs
CIP #111009 / BCE Score: 75.70 | | |
Not available
|
Not available
|
|
2026-126
| 1 | C. | | Resolution | Requisition No. REQ-0007184
Hubbell Southfield CSO Facility Improvements
Federally Funded CIP #273001 / BCE Score: 75.70 | | |
Not available
|
Not available
|
|
2026-127
| 1 | D. | | Resolution | Proposed Change Order No. 3
Contract No. 2102000/SCN-0000284
Emergency and Urgent Sewer Evaluation, Repair and Rehabilitation
CIP #260209/BCE Score: 61.30 | | |
Not available
|
Not available
|
|
2026-128
| 1 | E. | | Resolution | Proposed Amendment No. 7
Contract No. 1903601/SCN-0000356
Yard Piping Engineering Services
CIP #216006/BCE: 79.00 | | |
Not available
|
Not available
|
|
2026-129
| 1 | F. | | Resolution | Proposed Amendment No. 1
Contract No. 2003443/SCN-0000377
Study and Design Conveyance System
CIP #260206/BCE Score: 57.60 / CIP #260510/BCE Score: 73.80 | | |
Not available
|
Not available
|