2025-125
| 1 | A. | | Minutes | March 12, 2025 Operations and Resources Committee Meeting Minutes (Draft) | | |
Not available
|
Not available
|
2025-124
| 1 | A. | | Communication | Receipt of Correspondence | | |
Not available
|
Not available
|
2025-110
| 1 | A. | | Resolution | Proposed Change Order No. 1
Contract No. 2201255/SCN-0000412
Springwells Water Treatment Plant 1958 Flocculator Replacement
CIP #114017 / BCE Score: 89.70 | | |
Not available
|
Not available
|
2025-111
| 1 | B. | | Resolution | Proposed Change Order No. 1
Contract No. 2000279/SCN-0000213
Springwells Water Treatment Plant Flocculator Drive Replacement
CIP #114017 / BCE Score: 89.70 | | |
Not available
|
Not available
|
2025-112
| 1 | C. | | Resolution | Requisition Nos. REQ-0002565, REQ-0003295, REQ-0003302, REQ-0003341, REQ-0003401
Aluminum Sulphate
O&M | | |
Not available
|
Not available
|
2025-113
| 1 | D. | | Resolution | Requisition No. 2401015/REQ-0000333
Design Build for 96-Inch Water Transmission Main Relocation Phase 3
CIP #122004 / BCE Score: 77.50 | | |
Not available
|
Not available
|
2025-122
| 1 | E. | | Resolution | Requisition No. REQ-0001735
Ferric Chloride
O&M | | |
Not available
|
Not available
|
2025-123
| 1 | F. | | Resolution | Proposed Amendment No. 1
Contract No. 2202790/SCN-0000382
WRRF Improvements to Sludge Feed Pumps at Dewatering Facilities
CIP #213006/BCE Score: 76.60 | | |
Not available
|
Not available
|
2025-128
| 1 | G. | | Resolution | Proposed Change Order No. 2
Contract No. 2201744/SCN-0000118
Front Entrance Rehabilitation at the Water Resource Recovery Facility
CIP #260903 / BCE Score: 52.40 | | |
Not available
|
Not available
|
2025-127
| 1 | H. | | Resolution | Requisition No. REQ-0000348
Southeast Michigan Flood and Storm Damage Reduction General Investigation Study
O&M | | |
Not available
|
Not available
|