Great Lakes Water Authority Logo
File #: 2023-256    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/29/2023 In control: Board of Directors
On agenda: 7/26/2023 Final action: 7/26/2023
Title: Proposed Amendment No. 4 Contract No. GLWA-CS-060 Study/Design of an Upgraded Sludge Conveyance System and Lighting Improvements at the Detroit Wastewater Treatment Plant CIP #213007 / BCE Score: N/A
Sponsors: Navid Mehram, Christopher Nastally
Indexes: Wastewater Operations

Title
Proposed Amendment No. 4
Contract No. GLWA-CS-060
Study/Design of an Upgraded Sludge Conveyance System and Lighting Improvements at the Detroit Wastewater Treatment Plant
CIP #213007 / BCE Score: N/A

Body
Agenda of: July 26, 2023
Item No.: 2023-256
Amount: Original Contract $1,990,000.00
Amendment No. 1 96,404.00
Amendment No. 2 0.00
Amendment No. 3 0.00
Proposed Amendment No. 4 0.00
Total Contract Amount $2,086,404.00


TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: June 29, 2023


RE: Proposed Amendment No. 4
Contract No.: GLWA-CS-060
Study/Design of an Upgraded Sludge Conveyance System and Lighting Improvements at the Detroit Wastewater Treatment Plant
Vendor: Black & Veatch Ltd. of Michigan


MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. GLWA-CS-060, Proposed Amendment No. 4, "Study/Design of an Upgraded Sludge Conveyance System and Lighting Improvements at the Detroit Wastewater Treatment Plant" with Black & Veatch Ltd. of Michigan, with no increase in cost for a total cost not to exceed $2,086,404.00 and for an increased duration of 215 days, for a total duration of 2,834 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
Black & Veatch Limited of Michigan was awarded the original contract to provide, study, design, and construction assistance to GLWA with a start work date of April 29, 2016. The main objective of the Black & Veatch consultant services contract was to restore sludge conveyance capacity lost due to the March 2016 fire damage while providing improved sludge conveyance from...

Click here for full text