File #: 2023-037    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/27/2023 In control: Board of Directors
On agenda: 2/22/2023 Final action: 2/22/2023
Title: Contract No. 2101878-1 HAZMAT Building Rehabilitation CIP #260901/BCE Score: 52.10
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Attachments: 1. 2101878-1.Procurement Board Report-RFB, 2. 2101878-1.Cost Tabulation - Notice of Respondents

Title

Contract No. 2101878-1

HAZMAT Building Rehabilitation

CIP #260901/BCE Score: 52.10

 

Body                     

Agenda of:                     February 22, 2023

Item No.:                     2023-037

Amount:                     $2,932,000.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     January 27, 2023

 

RE:                     Contract No.  2101878-1

                     HAZMAT Building Rehabilitation

                     Vendor:  LaSalle Construction Services

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2101878-1, “HAZMAT Building Rehabilitation” with LaSalle Construction Services, at a cost not to exceed $2,932,000.00 for a duration of 365 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The HAZMAT security specialists at the WRRF provide rapid response for all GLWA operations, including site security for the WRRF Chlorination and Dechlorination facility and any emergency response and management of actual or potential leaks or spills of hazardous substances at our facilities. The specialists occupy the existing HAZMAT building daily, with a maximum of 5-6 specialists at certain times. The HAZMAT facility is a single-story, steel-framed, and concrete block building, with metal roofing and siding, and a concrete slab on the ground floor. The building was built in the 1990’s with the vehicle garage added in 2003 with no updates since the installation of the building. The building is occupied 24 hours per day, seven days per week. The building has exceeded its useful life and a complete rehabilitation of the building is required.

JUSTIFICATION

The existing HAZMAT building is at the end of its service life. Improvements to the HAZMAT building will provide an updated building for the training and development of the HAZMAT staff.

The Wastewater Team also looked at this as an opportunity to make improvements to the existing fit and form of the building to ensure it could serve the needs of the HAZMAT team of the future. This includes adding garage space for emergency response vehicles, a new classroom and training area to keep our team up to date on all the latest techniques and skills needed to protect GLWA staff, and a dedicated area for monitoring GLWA WRRF and other GLWA facilities to provide enhanced security monitoring and improve GLWA HAZMAT and Security response times. Additionally, this space will provide updated kitchen and lavatory facilities as well as a storage area for GLWA HAZMAT gear. These improvements not only enhance the existing facility but prepare it for the future and enable it to better serve and protect GLWA staff.

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: Sewer Construction Fund

Cost Center: Wastewater

Expense Type: Construction (5421-892211.000-616900-260901)

Estimated Cost by Year and Related Estimating Variance: See table below.

Fiscal Year

FY 2024 Plan                                                                                                                                        $1,338,000.00

FY 2025 Plan                                                                                                                                   662,000.00

Financial Plan Estimate                                                                                              $2,000,000.00  

Proposed Contract Award                                                                                                2,932,000.00  

Estimating Variance                                                                                                          ($932,000.00)

The award of this contract creates a negative estimating variance of $932,000.00. This variance will be funded from capital reserves. Please note that the amounts above as per the Draft #2 FY2024-2028 CIP has $2,000,000.00 budgeted for project 260901.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on February 8, 2023. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.