Great Lakes Water Authority Logo
File #: 2022-599    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/14/2022 In control: Board of Directors
On agenda: 1/25/2023 Final action: 1/25/2023
Title: Proposed Change Order No. 1 Contract No. 1904449 Lake Huron Water Treatment Plant Pilot Plant Design Build Services CIP #111011 / BCE Score: N/A
Sponsors: Cheryl Porter
Indexes: Water Operations
Title
Proposed Change Order No. 1
Contract No. 1904449
Lake Huron Water Treatment Plant Pilot Plant Design Build Services
CIP #111011 / BCE Score: N/A

Body
Agenda of: January 25, 2023
Item No.: 2022-599
Amount: Original Contract $3,157,387.00
Proposed Change Order No. 1 0.00
Total Contract Amount $3,157,387.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: December 29, 2022

RE: Proposed Change Order No. 1
Contract No. 1904449
Lake Huron Water Treatment Plant Pilot Plant Design Build Services
Vendor: Brown and Caldwell Constructors


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1904449 Proposed Change Order No. 1 "Lake Huron Water Treatment Plant Pilot Plant Design Build Services" with Brown and Caldwell Constructors, with no increase in cost for a total cost not to exceed $3,157,387.00 and an increased duration of 365 days for a total duration of 1,095 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.


BACKGROUND
This proposed Change Order No. 1 will increase the Final Completion by 365 calendar days at no additional costs to GLWA. This extension is being added to allow for training and operational oversight by the Engineer included in the original scope of work. A supply chain delay in receiving control panels and I/O cards from Emerson resulted in construction delays. The delivery of the items was delayed approximately 167 days. For GLWA team members to have proper training and access to quality control and operational oversight for the units, the Final Completion date will be moved back.
JUSTIFICATION
Several Allen-Bradley components require...