Title
Proposed Amendment No. 2
Contract No. GLWA-CS-259
As-Needed Engineering Services for Concrete Testing, Geotechnical Soil Borings and other Testing Services, and Related Services
CIP #380700 / BCE Score: 20.0
Body
Agenda of: June 22, 2022
Item No.: 2022-223
Amount: Original Contract $2,130,721.54
Amendment No. 1 0.00
Proposed Amendment No. 2 0.00
Total Revised Contract $2,130,721.54
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Interim Chief Executive Officer
Great Lakes Water Authority
DATE: May 27, 2022
RE: Proposed Amendment No. 2
Contract No. GLWA-CS-259
As-Needed Engineering Services for Concrete Testing, Geotechnical Soil Borings and other Testing Services, and Related Services
Vendor: Somat Engineering, Inc.
MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. GLWA-CS-259 Proposed Amendment No. 2 "As-Needed Engineering Services for Concrete Testing, Geotechnical Soil Borings and other Testing Services, and Related Services" with Somat Engineering, Inc., with no increase in cost, for a total cost not to exceed $2,130,721.54 and an increased duration of 321 days for a total contract duration of 1,718 days; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
Contract No. GLWA-CS-259 is an engineering services contract that GLWA has used for the design and construction administration of three water transmission main projects in which two of the projects are currently under construction. The two projects include the Wick Road 48-Inch Water Transmission Main Project, and the Park-Merriman 24-Inch Water Transmission Main Project. The durations of these two construction projects have been extended ...
Click here for full text