File #: 2022-166    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/26/2022 In control: Board of Directors
On agenda: 5/25/2022 Final action: 5/25/2022
Title: Proposed Change Order No. 3 Contract No. 1803621 Wick Road 48-Inch Water Transmission Main CIP #122006 / BCE Score: 54.2
Sponsors: Cheryl Porter
Indexes: Water Operations
Title
Proposed Change Order No. 3
Contract No. 1803621
Wick Road 48-Inch Water Transmission Main
CIP #122006 / BCE Score: 54.2

Body
Agenda of: May 25, 2022
Item No.: 2022-166
Amount: Original Contract $20,962,361.00
Change Order No. 1 1,217,151.00
Change Order No. 2 549,032.40
Proposed Change Order No. 3 460,000.00
Total Revised Contract $23,188,544.40

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Interim Chief Executive Officer
Great Lakes Water Authority

DATE: April 29, 2022

RE: Proposed Change Order No. 3
Contract No. 1803621
Wick Road 48-Inch Water Transmission Main
Vendor: Ric-Man Construction, Inc.


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. 1803621 Proposed Change Order No. 3 "Wick Road 48-Inch Water Transmission Main" with Ric-Man Construction, Inc., with an increase of $460,000.00 for a total cost not to exceed $23,188,544.40 and an increased duration of 365 days for a total duration of 1,389 days; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote.


BACKGROUND
GLWA Contract No. 1803621, Wick Road 48-inch Water Transmission Main, involves constructing approximately 17,000 linear feet of 48-inch diameter water transmission main parallel to an existing transmission main to provide redundancy between GLWA's Wick Road and Ypsilanti Booster Stations. To date, Ric-Man Construction has installed roughly 16,500 linear feet of pipe and remaining work includes interconnections between the new and existing transmission main. This Proposed Change Order No. 3 requests that 365 days be added to final contract completion. This additional time will allow for the completion of the remaining three (3) int...