File #: 2022-133    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/1/2022 In control: Board of Directors
On agenda: 4/27/2022 Final action: 4/27/2022
Title: Contract No. 2100236 Reservoir Inspection, Design, Construction Administration, Resident Project Representative (RPR) Services CIP #170802 / BCE Score: N/A
Sponsors: Cheryl Porter
Indexes: Water Operations
Attachments: 1. 2100236 Procurement Board Report, 2. 2100236 Cost Tabulation

Title

Contract No. 2100236

Reservoir Inspection, Design, Construction Administration, Resident Project Representative (RPR) Services

CIP #170802 / BCE Score: N/A

Body

Agenda of:                     April 27, 2022

Item No.:                     2022-133

Amount:                     $10,778,785.00

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Interim Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     April 1, 2022

 

RE:                                          Contract No. 2100236

                                          Reservoir Inspection, Design, Construction Administration, Resident Project Representative (RPR) Services

                                          Vendor:  Brown and Caldwell, LLC

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. 2100236 “Reservoir Inspection, Design, Construction Administration, RPR Services” with Brown and Caldwell, LLC, at a cost not to exceed $10,778,785.00 for a duration of 2,071 days; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND

GLWA operates and maintains 30 finished water reservoirs and administers a reservoir inspection and rehabilitation program under CIP No. 170800. The Michigan Department of Environment, Great Lakes, and Energy (EGLE) requires that finished water reservoirs are inspected every five years to ensure the reservoirs comply with sanitary requirements and are structurally sound. The scope of services under this contract (CIP No. 170802) includes inspecting and improving up to 15 of the system reservoirs and developing contract documents to competitively bid for construction activities. This contract will also provide construction administration phase assistance and resident project representation (RPR) services.

JUSTIFICATION

Finished water reservoirs must be inspected every five years to comply with EGLE regulatory requirements. Any critically deteriorated conditions or compromised sanitary conditions that are discovered must be corrected prior to returning a reservoir to service to ensure water quality is protected, and the structural integrity of the reservoirs is maintained.

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: Water Construction Bond

Cost Center: Water Engineering

Expense Type: Construction (5519-882111.000-617950-170802)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Fiscal Year

FY 2022 Plan Spend                                                                                                         $     469,000.00

FY 2023 Plan Spend                                                                                                             1,066,000.00

FY 2024 Plan Spend                                                                                                             1,069,000.00

FY 2025 Plan Spend                                                                                                             1,066,000.00

FY 2026 Plan Spend                                                                                                             1,066,000.00

FY 2027 Plan Spend                                                                                                                516,000.00

Financial Plan Estimate                                                                                                         $  5,252,000.00

Proposed Contract Award                                                                                                           10,778,785.00

Estimating Variance                                                                                                                              $ (5,526,785.00)

This proposed contract is being funded from the unallocated Program 170800 - System-Wide Finished Water Reservoir Inspection, Design and Rehabilitation balance identified in FY 2023 - 2027 CIP Plan. 

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on April 13, 2022.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.