File #: 2022-099    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/2/2022 In control: Board of Directors
On agenda: 3/23/2022 Final action: 3/23/2022
Title: Proposed Amendment No. 2 Contract No. GLWA-CS-300 Financial Automation Solution Services O&M
Sponsors: Jeffrey Small
Indexes: Information Technology

Title

Proposed Amendment No. 2

Contract No. GLWA-CS-300

Financial Automation Solution Services                     

O&M

 

Body

Agenda of:                     March 23, 2022

Item No.:                     2022-099

Amount:                     Original Contract                                                               $573,601.12

                                          Amendment No. 1                                                                 218,403.10 

                                          Proposed Amendment No. 2                       388,367.55

                                          Total Revised Contract                             $1,180,371.77

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                     Interim Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     March 2, 2022

 

RE:                                          Proposed Amendment No. 2

                     Contract No. GLWA-CS-300

                     Financial Automation Solution Services

                     Vendor:  Tagetik North America, LLC

 

                     

MOTION

Upon recommendation of Jeffrey E. Small, Chief Information Officer, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. GLWA-CS-300, Proposed Amendment No. 2,Financial Automation Solution Serviceswith Tagetik North America, LLC, at an increased cost of $388,367.55 for a total cost not to exceed $1,180,371.77 and for an increased duration of three years for a total duration of six years; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

BACKGROUND

The primary financial system, BS&A, was implemented at the start of GLWA’s operations in 2016. BS&A has a limited capacity for financial and budget reporting and does not meet GLWA’s ongoing business needs. Tagetik’s Financial Automation Solution was selected through an open competitive solicitation process with contract execution completed in March 2019 to improve our budgeting process and expand reporting capability. A contract amendment added enhanced reporting for accounts payable, purchase order, fixed asset, cash receipting, utility billing, cost of services, and administrative cost allocations. This system will be replaced with the new Workday Enterprise Resource Planning (ERP) system.

JUSTIFICATION

This amendment will enable GLWA to continue to use Tagetik as a reporting system until GLWA implements the new Workday (ERP) system.  The go-live date for the financial and budgeting modules of Workday is currently estimated to take place in July 2024.  Because the new system is not expected to be live until at least July 2024, this amendment is for additional licensing for a three (3) year term to provide GLWA with time to transition from Tagetik to its new ERP system.  

 

PROJECT MANAGEMENT STATUS

Original Contract Time                                           1,096 days (03/22/2019 - 03/21/2022)

Amendment 1                                                                             N/A

Proposed Amendment No. 2                     1,096 days (03/22/2022 - 03/21/2025)

New Contract Time                                                                2,192 days (03/22/2019 - 03/21/2025)

 

PROJECT ESTIMATE

Original Contract Price                                                                $573,601.12

Amendment No. 1                                                                                         218,403.10

Proposed Amendment No. 2                                            388,367.55

New Contract Total                                                                        $1,180,371.77

 

 

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this contract.      

Funding Source: Operations & Maintenance (O&M) Budget  

Cost Center(s): IT Business Productivity Systems (883341) 

Expense Type(s): Repairs & Maintenance - Software (5910-883341.000-622302-WS7900)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Fiscal Year                                                                                                                                                                         Amount

 

FY 2019 Budget (Prorated)                                                                                    $66,000.35

FY 2020 Budget                                                                                                                               264,001.41

FY 2021 Budget                                                                                                                              264,001.41

FY 2022 Budget                                                                                                                               230,365.02

FY 2023 Financial Plan                                                                                                         129,455.85

FY 2024 Financial Plan                                                                                                         129,455.85

FY 2025 Financial Plan (Prorated)                                                                 97,091.88

 

Financial Plan Forecast                                                                                          $1,180,371.77

                     

Proposed Contract Amount                                                                      $1,180,371.77

                     

Variance (positive/ (negative))                                                                                                          -  

 

COMMITTEE REVIEW

This item is being presented directly to the full Board of Directors.

SHARED SERVICES IMPACT

 This item does not impact the shared services agreement between GLWA and DWSD.