File #: 2022-020    Version: 1 Name:
Type: Presentation Status: Filed
File created: 1/19/2022 In control: Board of Directors
On agenda: 1/26/2022 Final action: 1/26/2022
Title: Presentation of the FY 2023 through FY 2027 Capital Improvement Plan
Sponsors: Jody Caldwell, Dima El-Gamal
Indexes: Planning Services
Attachments: 1. CIP 23-27 Board Presentation, 2. FINAL - GLWA 2023-2027 CIP_Document_01.19.2022, 3. Appendix A_Water, 4. Appendix B_Wastewater, 5. Appendix C_Centralized Svc, 6. CIP_HowtoNavigate, 7. Appendix E_Validation Report, 8. Appendix F_Equation Tech Memo

Title

Presentation of the FY 2023 through FY 2027 Capital Improvement Plan

 

Body

Agenda of:                      January 26, 2022

Item No.:                     2022-020                                                                                                                                                                                                                  

 

TO:                                          The Honorable

Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

                                          Interim Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     January 19, 2022

 

RE:                     Presentation of the FY 2023 through FY 2027 Capital Improvement Plan

MOTION

 

Upon recommendation of Jody Caldwell, Interim Chief Planning Officer, The Board of Directors for the Great Lakes Water Authority (GLWA), receives and files the presentation of the Capital Improvement Plan Discussion Draft #2 (FY2023 to FY2027), refers the plan to the Capital Planning Committee for their review and recommendation to the full Board of Directors, and authorizes the Chief Executive Officer to take such other action as may be necessary to accomplish the intent of this vote. 

JUSTIFICATION

A capital improvement plan addresses the following objectives.

1.  Identifies an organization’s priorities within available resources over a multiple year period. 

2. Communicates the scope, funding, and timing to stakeholders, coordinating agencies, investors, and the public. 

3.  Encompasses stakeholder engagement in its development.

4.  Aligns with strategic objectives of the organization, including effective capital 

     delivery and regulatory compliance at the lowest cost of capital investment.

 

BUDGET IMPACT

The FY 2023 through FY 2027 Capital Improvement Plan identifies $965.6 million of water system capital improvements and $761.7 million of sewer system improvements. 

COMMITTEE REVIEW

The Capital Planning Committee Reviewed Preliminary Drafts of the CIP on October 19, 2021 and December 14, 2021.