File #: 2022-014    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/7/2022 In control: Board of Directors
On agenda: 1/26/2022 Final action: 1/26/2022
Title: Approval of Cost Sharing Agreement and Exhibit A-1 between the City of Detroit, Water and Sewerage Department, and GLWA
Sponsors: Randal Brown
Indexes: General Counsel

 

Title

Approval of Cost Sharing Agreement and Exhibit A-1 between the City of Detroit, Water and Sewerage Department, and GLWA

 

Body

Agenda of:                      January 26, 2022

Item No.:                     2022-014

Amount:                                                                                                                                                                                                                                                            

 

TO:                                          The Honorable

Board of Directors

Great Lakes Water Authority

 

FROM:                     Suzanne R. Coffey, P.E.

Interim Chief Executive Officer

Great Lakes Water Authority

 

DATE:                     January 7, 2022

 

RE:                     Approval of Cost Sharing Agreement and Exhibit A-1 between the City of Detroit, Water and Sewerage Department, and GLWA

                                          

MOTION

 

Upon recommendation and opinion of Suzanne R. Coffey, Interim Chief Executive Officer. and Randal M. Brown, General Counsel, the Board of Directors for the Great Lakes Water Authority (GLWA):

 

1)                     Approves the execution of the Cost Sharing Agreement between the City of Detroit, Water and Sewerage Department and GLWA; and

 

2)                     Approves the reimbursement of costs outlined Exhibit A-1 with a 10% allowance above the estimated costs; and

 

3)                     Authorizes the Interim Chief Executive Officer to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

JUSTIFICATION

Through regular communication between DWSD and GLWA’s administrations, the parties identified opportunities to share costs associated with projects that benefit both DWSD and GLWA. In order to track these opportunities and standardize the paperwork associated with these projects, the parties desire to enter into a Cost Sharing Agreement. With an underlying agreement in place, the parties would amend the Agreement through the completion of the Exhibit A-# template.  Exhibit A will be sequentially numbered, A-1, A-2, A-3…A-10, to reflect a new project and the terms of the cost sharing between the parties. 

 

If the underlying Agreement is approved, “Exhibit A-#” would be presented to the Board of Water Commissioners or GLWA Board of Directors, consistent with contract authorization policies of the two organizations. For example, and consistent with GLWA’s Procurement Policy, GLWA would present an “Exhibit A-#” to the Board if the amount of GLWA’s cost sharing reimbursement to DWSD exceeded $1 million or the project would last more than 5 years.

 

Here, Exhibit A-1 meets the Board approval requirements for both organizations and therefore is being presented to the Board of Water Commissioners and GLWA’s Board of Directors. Exhibit A-1 relates to design work associated with replacement and rehabilitation of the aggregate utilities along E. Jefferson, which has been a discussion point for the last few years due to the expected pavement replacement work along the full reach of E. Jefferson Avenue.  The upcoming pavement work is an opportunity to renew and replace the underground utilities along East Jefferson, including regional and local water mains. The allocation of costs, per design task, is as follows:

 

Design Task #1: West of Water Works Park

Description: Installation of new 12-inch mains along Jefferson Ave to replace existing distribution mains

Allocation:100% DWSD

Estimated DWSD ($): 843,601

Estimated GLWA ($): 0

Estimated Extended Total ($): 843,601

 

Design Task #2: East of Water Works Park

Description: Replacement or rehabilitation of existing 16-inch, 12-inch, and 8-inch distribution mains from WWP to Gray Street and other select locations along Jefferson

Allocation: 100% DWSD

Estimated DWSD ($): 287,447

Estimated GLWA: 0

Estimated Extended Total ($): 287,447

 

 

Design Task #3: West of Water Works Park

Description: Replacement of 48-inch GLWA main from WWP to Downtown, meter vaults and pressure reducing valve vaults, retirement of one existing 42-inch GLWA main and one 42-inch DWSD main.

Allocation: 20% DWSD 80% GLWA

Estimated DWSD ($): 426,181

Estimated GLWA ($): 1,683,621

Estimated Extended Total ($): 2,109,802

 

Design Task #4: East of Water Works Park

Description: Replacement of the existing 8-inch main along Jefferson from Dickerson Avenue to Alter with 16-inch main

Allocation: 100% DWSD

Estimated DWSD ($): 126,750

Estimated GLWA ($): 0

Estimated Extended Total ($): 126,750

 

Design Task #5: Hydraulic Modelling

Allocation: 100% GLWA

Estimated DWSD ($): 0

Estimated GLWA ($): 23,875

Estimated Extended Total ($): 23,875

 

Design Task #6: Geotechnical Investigation

Allocation: 53% DWSD 47% GLWA

Estimated DWSD ($): 134,086

Estimated GLWA ($): 121,193

Estimated Extended Total ($): 255,279

 

Design Task #7: Subsurface Utility Engineering (SUE) Allowance

Allocation: 100% GLWA

Estimated DWSD ($): 0

Estimated GLWA ($) 185,643

Estimated Extended Total ($): 185,643

 

Design Task #8: Potholing Allowance

Allocation: 100% GLWA

Estimated DWSD ($): 0

Estimated GLWA ($): 207,627

Estimated Extended Total ($): 207,627

 

 

 

Total Estimated Project Costs

Estimated DWSD ($): 1,818,065

Estimated GLWA ($): 2,221,959

Estimated Extended Project Costs Total: 4,040,024

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: Water Construction Fund

Cost Center: Water Field Engineering

Expense Type: Construction (5519-882411.000-617950-122019)

 

Estimated Cost by Year and Related Estimating Variance:  See table below.

 

Fiscal Year

FY 2022 Plan                                                                                         $     613,000.00

FY 2023 Plan                                                                                                 782,000.00

FY 2024 Plan                                                                                                686,000.00

FY 2025 Plan                                                                                                684,000.00

FY 2026 Plan                                                                                                684,000.00

FY 2027 Plan                                                                                                  28,000.00

  Financial Plan Estimate                                                                                               $  3,477,000.00

Proposed Contract Award                                                                                                             2,221,959.00

Balance reserved for services during construction                     $  1,255,041.00

Plan amounts above as per Draft 2 of the FY 2023 - 2027 CIP Plan.

 

 

 

COMMITTEE REVIEW

This matter was presented to the Operations and Resources Committee on January 12, 2022.   The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This request does not impact the Shared Services Agreement.