File #: 2021-319    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/4/2021 In control: Board of Directors
On agenda: 9/1/2021 Final action: 9/1/2021
Title: Proposed Change Order No. 2 Contract No. 1803621 Wick Road 48-Inch Water Transmission Main CIP# 122006 / BCE Score: 54.2
Sponsors: Cheryl Porter, Grant Gartrell
Indexes: Water Operations

Title

Proposed Change Order No. 2

Contract No. 1803621

Wick Road 48-Inch Water Transmission Main

CIP# 122006 / BCE Score: 54.2

 

Body

Agenda of:                     September 1, 2021

Item No.:                     2021-319

Amount:                     Original Contract                                                               $20,962,361.00

                                          Change Order No. 1                                              1,217,151.00

                                          Proposed Change Order No. 2                             549,032.40

                                          Total Revised Contract                                          $22,728,544.40

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     August 4, 2021

 

RE:                                          Proposed Change Order No. 2

                                          Contract No. 1803621

                                          Wick Road 48-Inch Water Transmission Main

                                          Vendor:  Ric-Man Construction, Inc.

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1803621 Proposed Change Order No. 2 “Wick Road 48-Inch Water Transmission Main” with Ric-Man Construction, Inc., with an increased cost of $549,032.40 for a total cost not to exceed $22,728,544.40 with an increased duration of 160 days for a total duration of 1,024 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

BACKGROUND

GLWA Contract No. 1803621, Wick Road 48-inch Water Transmission Main, involves constructing approximately 17,000 linear feet of 48-inch diameter water transmission main parallel to an existing transmission main to provide redundancy between GLWA’s Wick Road and Ypsilanti Pumping Stations. The contract was awarded to Ric-Man Construction Inc., and the notice to proceed issued on August 26, 2019. As of June 2021, about 16,000 linear feet of the contract’s 17,000 linear feet of the 48-inch transmission main has been installed. Remaining work consists of installing 280 feet of transmission main beneath the CSX railroad and installing interconnects between the existing and new transmission mains, including the associated gate valves.

JUSTIFICATION

The current contract specifies removing roughly 70 linear feet of existing 48-inch water main near the Wick Road Pumping Station. After removal, the contractor will install a new 42-inch double-disc gate valve that will give GLWA the ability to isolate the parallel water mains feeding the Ypsilanti Pumping Station. Upon field verification of the existing 48-inch main scheduled for removal, it was discovered that the main was not restrained in this area. For GLWA to obtain a restraint pipeline system at the new 48-inch gate valve, roughly 300 linear feet of additional existing water main needs to be removed and replaced, including road restoration which is required to facilitate the additional pipe restraint. By restraining this section of pipe upstream and downstream of the 48-inch gate valve, GLWA is provided greater system resiliency at this isolation point in a closed valve situation, mitigating future safety concerns for workers when this main is isolated for maintenance and future replacement. The substantial completion date is being extended due to the system constraints during the high demand season and the contractor’s inability to complete the final interconnections at three locations. The completion of the final connections will begin at the low demand season followed by final site restoration. Therefore, this proposed change order requests that the final completion date be extended to June 15, 2022.

PROJECT MANAGEMENT STATUS

Original Contract Time                                                                   730 days

Change Order No. 1                                                                    134 days

Proposed Change Order No. 2                                             160 days

New Contract Time                                                                                     1,024 days

 

 

PROJECT ESTIMATE

Original Contract Price                                           $ 20,962,361.00

Change Order No. 1                                                1,217,151.00

Proposed Change Order No. 2                              549,032.40

New Contract Total                                                                $ 22,728,544.40

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.          

Funding Source: Water Construction Bond

Cost Center: Field Engineering

Expense Type: Construction (5519-882411.000-616900-122006)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                                        $20,962,361.00

Change Order No. 1                                                                                      1,217,151.00

Proposed Change Order No. 2                                                                    549,032.40

New Contract Total                                                                                                         22,728,544.40

Amended Financial Plan Estimate                                          22,179,512.00

Estimating Variance                                                                                             ($    549,032.40)

The award of this change order to the vendor creates a negative estimating variance of $549,032.40. This variance will be funded from capital reserves.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on August 11, 2021.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.