File #: 2021-166    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/30/2021 In control: Board of Directors
On agenda: 5/26/2021 Final action: 5/26/2021
Title: Proposed Change Order No. 2 Contract No. GLWA-CON-149 Emergency Sewer Repair
Sponsors: Cheryl Porter, Todd King
Indexes: Water Operations
Attachments: 1. memorandum - 20210504 - CON-149 Change Order 2 replacement contract timeline

Title

Proposed Change Order No. 2

Contract No. GLWA-CON-149

Emergency Sewer Repair

 

Body

Agenda of:                     May 26, 2021

Item No.:                     2021-166

Amount:                     Original Contract                                                               $26,800,000.00

                                          Change Order No. 1                                            26,800,000.00

                                          Proposed Change Order No. 2                                       0.00

                                          Total Contract                                                               $53,600,000.00

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     May 4, 2021

 

RE:                                          Proposed Change Order No. 2

                                          Contract No. GLWA-CON-149

                                          Emergency Sewer Repair

                                          Vendor:  Inland Waters Pollution Control, Inc.

 

                     

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. GLWA-CON-149 Proposed Change Order No. 2 “Emergency Sewer Repair” with Inland Waters Pollution Control, Inc., with no increase in cost for a total cost not to exceed $53,600,000.00 and an increased duration of 348 days for a total contract duration of 1,809 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

BACKGROUND

The GLWA sewer system (approximately 180 miles of sewers ranging from 48” through 168”) is eighty (80) years old or more. Because of the age of the sewers, they are deteriorating at a faster rate. Some are rated at higher PACP (Pipeline Assessment Certification Program) rating, and immediate emergency action is often required. Sewer rehabilitation services are necessary to repair plugged, damaged, and collapsed sewers to avoid basement flooding, and maintain the flows within the wastewater conveyance system.

The purpose of this contract is to provide the means of inspection, sewer lining and open cut repair of failed sewers and in-place rehabilitation of selected sewers using the procedures, methods, and equipment of the cured-in-place pipe lining process.

Project/Objectives

The project tasks are described as follows:

A.                     Clean sewers, remove and dispose of sludge and all internal debris, including root intrusion, protruding taps and minerals deposits from pipelines. Perform inspections of sewer by experienced personnel trained in locating breaks, obstacles, and service connections by closed circuit television or man entry.

B.                     Prepare the televised sewer information report, and review with GLWA staff to determine the necessary repair requirements and establish thickness design parameters.

C.                     Provide design and corresponding costs for GLWA review and approval.

D.                     Acquire all necessary permits required to complete each task, at no extra cost to GLWA.

E.                     Provide traffic control and public notification.

F.                     Provide bypass pumping, if needed, in order to maintain services to customers upstream and downstream of pipeline being reconstructed.

G.                     Trim any protruding taps to achieve smooth lining of the sewers, as part of the lining operation.

H.                     Line the sewer using suitable resin systems conforming to the requirements of the current standard specifications for rehabilitation of existing pipelines and conduits.

I.                     Furnish clean up and restoration of the site.

J.                     Remove and dispose of all the lining material left inside the sewers and/or manhole.

K.                     Conduct inspection of lined sewers via TV camera and provide as-built drawings.

At the request of GLWA, the Contractor will also provide the following services:

1.                     Rehabilitate sewers by method of slip lining.

2.                     Rehabilitate sewers by the method of pipe bursting.

JUSTIFICATION

Most of the GLWA existing sewers within the collection system are older than 80 years. Due to the age and deterioration of the sewer pipes, immediate repair and/or rehabilitation is often required. CON-149 is necessary to continue the sewer emergency repairs and rehabilitations.

PROJECT MANAGEMENT STATUS

Original Contract Time                                                                  730 days

Change Order No. 1                                                                 731 days

Proposed Change Order No. 2                                            348 days

New Contract Time                                                                          1,809 days

PROJECT ESTIMATE

Original Contract Price                                                                $26,800,000.00

Change Order No. 1                                                                   26,800,000.00

Proposed Change Order No. 2                                                             0.00

New Contract Total                                                                                     $53,600,000.00

FINANCIAL PLAN IMPACT

Summary: The proposed change order with Inland Waters Pollution Control, Inc. encompasses Capital Improvement Plan and Operations & Maintenance expenses. The value of the contract is within the current financial plan in total. Sufficient funds will be provided in the Operations & Maintenance (O&M) and CIP financial plan for this contract related to contractual operating services.

Funding Source: Operations & Maintenance (O&M) Budget, CIP 260201

Cost Centers(s): Field Services Operations..Centralized Services cost center 882431

Expense Type(s): Contractual Operating Services (617900); Construction (616900)

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on May 12, 2021.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.