Skip to main content
Great Lakes Water Authority Logo
File #: 2021-126    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/6/2021 In control: Board of Directors
On agenda: 4/28/2021 Final action: 4/28/2021
Title: Proposed Change Order No. 4 Contract No. GLWA-CON-250 Pumping Station No. 1 Rack & Grit and MPI 1 & Jefferson Sampling Stations Improvements CIP # 211004
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title
Proposed Change Order No. 4
Contract No. GLWA-CON-250
Pumping Station No. 1 Rack & Grit and MPI 1 & Jefferson Sampling Stations Improvements
CIP # 211004

Body
Agenda of: April 28, 2021
Item No.: 2021-126
Amount: Original Contract: $6,193,801.41
Change Order No. 1: 0.00
Change Order No. 2: 0.00
Change Order No. 3: 0.00
Proposed Change Order No. 4: 0.00
Total Revised Contract: $6,193,801.41

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority

DATE: April 6, 2021

RE: Proposed Change Order No. 4
Contract No. GLWA-CON-250
Pumping Station No. 1 Rack & Grit and MPI 1 & Jefferson Sampling Stations Improvements
Vendor: Weiss Construction Company, LLC
Designer: Alfred Benesch & Company

MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract GLWA-CON-250 Proposed Change Order No. 4 "Pumping Station No. 1 Rack & Grit and MPI 1 & Jefferson Sampling Stations Improvements" with Weiss Construction Company, LLC for no increase in cost, for a total cost not to exceed $6,193,801.41 and an increased duration of 61 days to the final completion date for a total contract duration of 1247 days, and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND
On November 13, 2013, the Detroit Water and Sewerage Department (DWSD) entered into Contract No. PC-789 (Pumping Station No.1 Rack and Grit and Main Plant Influent (MPI) 1 and Jefferson Sampling Stations Improvements) with Weiss Construction Company, LLC in the amount of $20,335,000.00. It was an open competitive lowest bid contract. ...

Click here for full text