File #: 2021-083    Version: 1 Name:
Type: Resolution Status: Passed
File created: 3/2/2021 In control: Board of Directors
On agenda: 3/24/2021 Final action: 3/24/2021
Title: Proposed Change Order No. 2 Contract No. 1803776 Relocation of the Analytical Lab Operations to the GLWA - Water Resource Recovery Facility (WRRF) CIP #214001
Sponsors: Navid Mehram, Daniel Alford
Indexes: Wastewater Operations
Title
Proposed Change Order No. 2
Contract No. 1803776
Relocation of the Analytical Lab Operations to the GLWA - Water Resource Recovery Facility (WRRF)
CIP #214001

Body
Agenda of: March 24, 2021
Item No.: 2021-083
Amount: Original Contract $11,499,000.00
Change Order No.1 250,000.00
Proposed Change Order No. 2 100,000.00
Total Revised Contract $11,849,000.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority

DATE: March 2, 2021

RE: Proposed Change Order No. 2
Contract No. 1803776
Relocation of the Analytical Lab Operations to the GLWA - Water Resource Recovery Facility (WRRF)
Vendor: Commercial Contracting Corporation

MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1803776 Proposed Change Order No. 2, "Relocation of the Analytical Lab Operations to the GLWA-WRRF", with Commercial Contracting Corporation, at an increased cost not to exceed sum of $100,000.00 for a revised total cost not to exceed $11,849,000.00 and an increased duration of the final completion date by 90 days for a total revised contract duration of 720 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND
On September 9, 2019, the Great Lakes Water Authority awarded Contract No. 1803776 (Relocation of the Analytical Lab Operations to the GLWA-WRRF), to Commercial Contracting Corporation (CCC). The required substantial completion date of the project was September 8, 2020 and the required final completion date is March 8, 2021 with a contract amount of $11,499,000.00.

The scope of work includes renovation/reconfiguration of the current WRRF laboratory, admin...

Click here for full text