Title
Proposed Change Order No. 3 Final
Contract No. GLWA-CON-133
Water Production Flow Metering Improvements at Northeast, Southwest and Springwells Water Treatment Plants
CIP# 114003 / BCE Score: 50.6
Body
Agenda of: September 23, 2020
Item No.: 2020-306
Amount: Original Contract $6,876,833.00
Change Order No. 1 183,282.49
Change Order No. 2 0.00
Proposed Change Order No. 3 (212,878.93)
Total Revised Contract $6,847,236.56

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority

DATE: August 31, 2020

RE: Proposed Change Order No. 3 Final
Contract No. GLWA-CON-133
Water Plant Production Flow Metering Improvements at Northeast, Southwest and Springwells Water Treatment Plants
Vendor: LGC Global, Inc.

MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. GLWA-CON-133 Proposed Change Order No. 3 Final, "Water Plant Production Flow Metering Improvements at Northeast, Southwest, and Springwells Water Treatment Plants" with LGC Global, Inc., at a reduced cost of $212,878.93 for a total cost not to exceed of $6,847,236.56 and an increased duration of 45 days for a total contract duration of 1,081 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
Contract No. GLWA-CON-133 with Lakeshore Global Corporation (Contractor) is a construction contract for the rehabilitation and improvement of water production flow metering at the Northeast, Southwest, and Springwells water treatment plants. The work involves rehabilitating a total of 16 venturi-style flow meters and associated equipment at the aforementioned water treatment plants. The contract time commen...