File #: 2020-273    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/7/2020 In control: Board of Directors
On agenda: 8/26/2020 Final action: 8/26/2020
Title: Proposed Amendment 1 GLWA-SOQ-135A Security Infrastructure Improvements CIP# 341001/ 341002 / BCE N/A
Sponsors: W. Barnett Jones
Indexes: Security and Integrity
Attachments: 1. CIP Excerpts

Title

Proposed Amendment 1

GLWA-SOQ-135A

Security Infrastructure Improvements

CIP# 341001/ 341002 / BCE N/A

 

Body

Agenda of:                     August 26, 2020

Item No.:                     2020-273

Amount:                      Original Contract Price                                                    $ 7,604,479.08

                         Proposed Amendment No. 1                $ 5,101,903.10

                         New Contract Total                              $12,706,382.18

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     July 29, 2020

 

RE:                                          Proposed Amendment No. 1

                     Contract No.: GLWA-SOQ-135A

                     Security Infrastructure Improvements

                     Vendor:  Rotor Electric Company of Michigan, LLC

                     

MOTION

Upon recommendation of W. Barnett Jones, Chief Security and Integrity Officer, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. GLWA-SOQ-135A, Proposed Amendment No. 1 “Security Infrastructure Improvements” with Rotor Electric Company of Michigan, at an increased cost of $5,101,903.10 for a total cost not to exceed $12,706,382.18, and an increased duration of 294 days for a total contract duration of 1,389 days; and authorizes the CEO to take such other action as may be to accomplish the intent of this vote. 

BACKGROUND

Contract SOQ-135A involves Camera installations, perimeter intrusion detection, enhanced access controls within the GLWA system. This design project includes virtually every facility within the GLWA System (47 different sites) ranging from Freshwater Treatment Plants and WRRF to small Fresh and Sewage Pumping Stations and all of the CSO Basins.

The start work date for SOQ-135A was February 21, 2018 with a Final Completion Date of February 19, 2021 (1095 days). There was no substantial completion date defined as the project was a design and construction administration contract. The original sequence of design and construction was provided during the bidding process.

                     The base contract amount was defined based on an incomplete scope. Additional details were provided at the contract signing that could not be released through the bid process due to the confidential nature of the security improvements. These details specifically identified GLWA facilities and security specifications for the design and construction process.

 

                     The design duration took longer than expected due to unforeseen conditions such as incomplete/inaccurate as built documentation, and existing non-code compliant installations.

 

                     Additional design duration occurred as the anticipated cost of construction was getting too high, so redesign was required to reduce construction cost.

 

                     The original Construction budget of $6,000,000 was an estimate and has not matched the design projections.

 

                     To date, GLWA has under construction:

                     Belle Isle Intake Facility                                      731,360.82

                     Water Station Phase 1 (4 Sites)                          765,471.22

                     Water Station Phase 2 (5 Sites)                          695,168.26

                     Water Station Phase 3 (5 Sites)                          432,509.90

                     Water Station Phase 4 (4 Sites)                          423,244.21

                     Springwells WTP                                                 749,000.00

                     Water Resources Recovery Facility                  1,860,162.88

Total Under Construction (22 sites)                                               5,656,917.29

Construction Allowance Remaining:                                                343,082.71

                     The sites remaining to be constructed include:

                     CSO Phase 1 (4 Sites)                                           620,289.091

                     Southwest WTP                                                      661,730.461

                     Water Works Park WTP                                         979,777.962

                     Lake Huron WTP                                                 1,153,595.302

                     CSO Phase 2 (5 Sites)                                           780,000.003

                     Northeast WTP                                                       760,000.003

Total Remaining to be Constructed (13 Sites):                                    4,955,385.81

1.                     Design is complete and final pricing is established.

2.                     Preliminary design is complete pricing is rough estimate

3.                     Preliminary design is ongoing, this is a budgetary estimate

JUSTIFICATION

The SOQ-135A contract construction allowance of $6,000,000 was insufficient to provide the necessary security upgrades at all of the GLWA facilities. As such, an increase in the construction allowance is necessary to complete the work at all of the facilities. Commensurate with that is a need for additional administration cost to manage that additional construction.

                     Total Board request is $5,101,903.10 this is broken down as follows:

§                     Additional construction costs are $4,612,303.101.

                     CSO Phase 1:                                                                                                               $620,289.09

                     SW WTP Surveillance & Intrusion Detection               661,730.46

                     WWP WTP Surveillance & Intrusion Detection            979,770.96

                     LH WTP Surveillance & Intrusion Detection              1,153,595.30

                     NE WTP Surveillance & Intrusion Detection                 760,000.00

                     CSO Phase 2                                                                780,000.00

                     Total Construction Dollars Needed:                         $4,955,385.81

                     Remaining Allowance from base contract:                ($343,082.71)

§                     Additional Administration costs are $489,600.002.

§                     The new Substantial Completion date is 9/10 /2021

§                     The new Final Completion date is 12/09/2021

§                     The extended duration is 294 total days

1.                     Remaining to be constructed minus balance of existing Allowance

2.                     (3) People for 6 months for Administration

 

PROJECT MANAGEMENT STATUS

Original Contract Time                                              1,095 Days Three (3) years

Amendment No. 1                                                                  294 Days

New Contract Time                                                                1,389 Days

 

PROJECT ESTIMATE

Original Contract Price                                           $  7,604,479.08

Amendment No. 1                                                                    5,101,903.10

New Contract Total                                                                $12,706,382.18

 

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: Water Improvement and Extension Fund / Wastewater Improvement and Extension Fund

Cost Center: Security & Integrity (881201.000 / 891201.000)

Expense Type:                     Construction (5506-881201.000-616900-341001)

                                                               Construction (5404-891201.000-616900-341002)

 

Estimated Cost by Year and Related Estimating Variance:  See table below.

Original Contract Price                                                                                    $  7,604,479.08

Proposed Change Order No. 1                                                               $  5,101,903.10

New Contract Total                                                                                                         $12,706,382.18

Financial Plan Estimate 341001/341002                                            12,642,000.00

Negative Estimating Variance                                                    $      (64,382.18)                                                                                                                                                                                                                                                                                   

The award of this change order to the vendor creates a negative estimating variance of $64,382.18. This variance will be funded from capital reserves.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on August 12, 2020.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.