File #: 2020-272    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/7/2020 In control: Board of Directors
On agenda: 8/26/2020 Final action: 8/26/2020
Title: Contract No. 1902224 Design-Build Contract for CSO Facilities Structural Improvements CIP # 260614 (CSO Facilities)
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Attachments: 1. 1902224 - Procurement Board Report RFP, 2. 1902224 - Cost Summary, 3. CIP Plan 260614, 4. 1902224 - Cost Tabulation

 

Title

Contract No. 1902224

Design-Build Contract for CSO Facilities Structural Improvements

CIP # 260614 (CSO Facilities)

...Body                     

Agenda of:                      August 26, 2020                     

Item No.:                     2020-272

Amount:                      $12,055,334.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                      July 13, 2020                     

 

RE:                                           Contract No. 1902224

                                          Design-Build Contract for CSO Facilities Structural Improvements

                                                    Vendor:  Pullman SST, Inc

 

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1902224, “Design-Build Contract for CSO Facilities Structural Improvements” with Pullman SST, Inc., at a cost not to exceed Twelve Million Fifty Five Thousand Three Hundred Thirty Four Dollars ($12,055,334.00) for a duration of four years, and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

BACKGROUND

GLWA operates and maintains nine Combined Sewer Overflow (CSO) Facilities throughout the GLWA service area. These facilities were constructed from 1994 to 2011 averaging 18 years of age.  The location and age of each CSO facility are noted in the table below:

CSO Facility Name

Facility Address

Year Constructed

Hubbell-Southfield

16450 Rotunda Dr, Dearborn, MI 48120

1994

Seven Mile

19272 Shiawassee Rd., Detroit, MI 48219

1994

Puritan-Fenkell

23672 Fenkell, Detroit, MI 48214

1994

St. Aubin

2200 Atwater Detroit, MI 48207

1999

Leib

2188 Mt. Elliot, Detroit, MI 48207

2004

Baby Creek

9545 Dix Rd, Dearborn, MI 48120

2005

Conner Creek

11900 Freud, Detroit, MI 48214

2006

Belle Isle

2 Pleasure Dr., Detroit, MI 48207

2009

Oakwood

12082 Pleasant St., Detroit, MI 48217

2011

 

An initial structural inspection of the CSO Facilities was conducted by a structural engineering firm that identified various improvements needed for each facility to ensure the resiliency and proper operation of our facilities for the next 20-years.  The inspection identified amongst other things, settling brick/block walls in need of support, spalling concrete, concrete joints missing protective layers, efflorescence of brick/block walls, and cracked concrete which allows water infiltration and exfiltration. The findings can create structural instability if left unrepaired over time.  To improve delivery time so that repairs can be made efficiently, and can be addressed immediately, the design team elected to use the design-build delivery method for this project.  A design-build delivery method includes a detail assessment to identify all needed repairs, a prioritization list that will be agreed by GLWA and the Contractor, and design development with input from the builder prior to commencement of construction.  

As indicated in the table above, this project includes improvements to a DWSD owned facility, Belle Isle CSO Facility and Pump Station.  GLWA worked closely with DWSD staff during the preliminary engineering phase of this project to obtain approval of DWSD to have Belle Isle CSO and Pump Station included in the construction phases.  Preliminary engineering documents and cost estimates were reviewed by DWSD staff prior to DWSD requesting the Belle Isle CSO and Pump Station Facility to be included in the design/build phase of this project.  Collectively, GLWA and DWSD participated in evaluating proposals for this project and selecting the most qualified design-build team for this project as well as participating in contract negotiations.  After the contractor was selected and costs were negotiated, GLWA engaged DWSD again with actual project costs to again confirm that DWSD still wanted Belle Isle Facilities included in the project as well as discussed options that could be considered for inclusion of Belle Isle (reduced scope, inspection only, close coordination throughout).  On August 4th, DWSD indicated that Belle Isle facility would remain included in this project.  Overhead project costs of the work at Belle Isle facility were evaluated and represent 3.7% of the total project overhead costs.  Repairs will be made at Belle Isle Facility, as all other facilities, at the unit prices bid for the Contract.  GLWA will continue to engage DWSD throughout the course of this project to continue our excellent communication. DWSD shall pay the actual costs plus overhead for the Belle Isle Facilities improvements pursuant to a cost sharing agreement with GLWA.

JUSTIFICATION

In consideration that many of these assets are brick, block, concrete, and steel, they do not require maintenance at regular frequency because their rate of deterioration is substantially slower than mechanical equipment for example.  Therefore, proper asset management of a building, tank, or other large structure includes performing inspections to assess the integrity of these facilities to ensure the useful life of these assets is not just realized, but extended, and service is not interrupted unexpectedly.  As concrete or similar structures age they may develop cracks or other defects due to the environmental and other conditions they are subjected to constantly while in service (and even out of service - weather).  While they are generally designed to handle these conditions, over time they require periodic improvements to ensure reliability and resiliency of the structures.

To re-prepare these facilities for future uninterrupted service, the Design-Build Team (D/B Team) will perform a complete structural assessment at all nine GLWA CSO facilities.  The assessment report shall identify all structural repairs that are required to ensure a continued useful service life of a minimum of 20 years, provide estimated quantities for each type of repair, while prioritize each repair.  Following the assessment period, the D/B Team will work with GLWA to develop a three-year plan to identify the high priority repairs based on assessment report, within the funding available, and utilizing established unit prices under this Contract.  Based upon GLWA’s agreement, D/B team will provide design document for repairs to be implemented, including but not limited to drawings, technical specifications and calculations.  D/B team will perform the repairs over a three-year period (Phase 1, Phase 2, and Phase 3), working from highest to lowest priority.

The Work includes improvements to be designed, administered, and constructed by the D/B Contractor, inclusive of civil/site, architectural, and structural, engineering disciplines and construction trades, as may be applicable to complete the work.  The Work will be performed in following phases:

Phase

Duration from NTP Date

Completion of Assessment and Planning

6 months

Phase 1 Completion

18 months

Phase 2 Completion

30 months

Phase 3 Completion

42 months

Final Completion

48 months

 

 

 

FINANCIAL PLAN IMPACT

Summary: This project is eligible for funding from both Construction Improvement Plan (CIP) for the Sewer Fund (#5421) resources and Improvement & Extension Fund (I&E) Sewer Fund (#5404) resources.

Cost Center: Sewer Water Engineering

Estimated Cost by Year and Related Estimating Variance:  See table below.

Fiscal Year

FY 2019 Budget                                                                                                         $  335,000.00

FY 2020 Budget                                                                                                      44,000.00                                          

FY 2021 Budget                                                                                                          1,286,000.00

FY 2022 Budget                                                                                                5,788,000.00

FY 2023 Budget                                                                                                          4,460,000.00

FY 2024 Budget                                                                                                             622,000.00  

Financial Plan Estimate                                                                         12,535,000.00

Proposed Contract Award                                                                         12,055,334.00

Positive Estimate Variance                                                                  $479,666.00

 

Please note that the amounts above are per the Final Draft of the 2021 - 2025 CIP.

 

COMMITTEE REVIEW

 

This item was presented to the Operations and Resources Committee at its meeting on August 12, 2020.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

 

SHARED SERVICES IMPACT

 

This item does not impact the shared services agreement between GLWA and DWSD. However, there will be a cost sharing agreement between GLWA and DWSD, which will memorialize the scope and payment terms for the work at the Belle Isle Facilities.