File #: 2020-269    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/5/2020 In control: Board of Directors
On agenda: 8/26/2020 Final action: 8/26/2020
Title: Contract No. 2000746 Hydrofluorosilicic Acid O&M
Sponsors: Cheryl Porter, Terry Daniel
Indexes: Water Operations
Attachments: 1. 2000746 Procurement Report, 2. 2000746 Bid Tab

Title

Contract No. 2000746

Hydrofluorosilicic Acid

O&M

 

Body                     

Agenda of:                     August 26, 2020

Item No.:                     2020-269

Amount:                      $2,571,275.40                     

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     August 5, 2020

 

RE:                                          Contract No. 2000746

                                          Hydrofluorosilicic Acid

                                          Vendor:  PVS Nolwood Chemicals, Inc.

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2000746 “Hydrofluorosilicic Acid” with PVS Nolwood Chemicals, Inc., at a cost not to exceed $2,571,275.40 for a duration of three years; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

Hydrofluorosilicic acid (H2SiF7), concentration 23% by weight, or greater, is provided to GLWA’s five water treatment plants for water fluoridation. Water fluoridation increases the concentration of fluoride ions in drinking water to reduce dental caries (tooth decay).  The U.S. Public Health Service (PHS) and U.S. Environmental Protection Agency (EPA) recommends a fluoride level of 0.7 milligrams/liter (mg/L).

 

 

JUSTIFICATION

The hydrofluorosilicic acid chemical is added for the prevention of tooth decay.

FINANCIAL PLAN IMPACT

Summary: The proposed contract with PVS Nolwood Chemicals, Inc. encompasses an Operations & Maintenance expense only.  The FY 2021 budget and five-year financial plan was based on prior usage of all chemicals over the contract periods.  The value of the contract exceeds the financial plan in total.  Potential positive variances of other chemicals, as well as the use of this chemical, may vary by year. The financial plan will be adjusted accordingly during the FY 2022 budget preparation to accommodate the proposed contract amount. Sufficient funds will be provided in the Operations & Maintenance (O&M) financial plan for this contract related to operating supplies-chemicals.

Funding Source:  Operations & Maintenance (O&M) Budget  

Cost Center(s): Water Works Park ..............Water Operations cost center 882131

                           Springwells WTP…………….Water Operations cost center 882141

                           Northeast WTP……………..Water Operations cost center 882151

                           Southwest WTP……………...Water Operations cost center 882161

                           Lake Huron WTP………….....Water Operations cost center 882171

Expense Type: Operating Supplies - Chemicals (621600) 

Estimated Cost by Year and Related Forecasted Variance:  See table below. 

Fiscal Year                                                                                                                                                                         Amount

 

FY 2021 Budget                                                                                                                   $514,000

FY 2022 Financial Plan                                                                                                516,000

FY 2023 Financial Plan                                                                                                518,000 

                     Financial Plan Forecast                                                 $1,548,000                     

 

Proposed Contract Amount                                                                      $2,571,275

Variance (positive/ (negative))                                                                                $(1,023,275) 

 

SAVINGS, COST OPTIMIZATION, AND REVENUE ENHANCEMENT IMPACT

The award of this contract provides a variance of $1,023,275 ($1,548,000 financial plan forecast less $2,571,275 proposed contract amount). 

The actual usage of all chemicals fluctuates with changes in production, treatment volume, consumption, pumping and customer growth.  The result of the fluctuation may be more or less than estimated quantities forecasted with the use of each chemical and current market pricing.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on August 12, 2020.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.