File #: 2019-395    Version: 1 Name:
Type: Resolution Status: Passed
File created: 11/1/2019 In control: Board of Directors Workshop Meeting
On agenda: 12/11/2019 Final action: 12/11/2019
Title: Proposed Change Order No. 4 GLWA CS-071 Staff Augmentation
Sponsors: Jeffrey Small
Indexes: Information Technology

Title

Proposed Change Order No. 4

GLWA CS-071

Staff Augmentation

 

Body

Agenda of:                     December 11, 2019

Item No.:                      2019-395

Amount:                     Original Contract:                                                               $   822,280.00

                                          Change Order No. 1:                                          $   966,560.00

                                          Change Order No. 2:                                          $   990,920.00

                                          Change Order No. 3:                                          $   667,520.00

Proposed Change Order No. 4                      $   667,520.00

Total Revised Contract                                          $4,114,800.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     October 2, 2019

 

RE:                                          Proposed Change Order No. 4

 

                     Contract No.: 4000012 / 1903673 - GLWA-CS-071

                     Staff Augmentation

                     Vendor:  Data Consulting Group, Inc.

 

 

MOTION

Upon recommendation of Jeffrey E. Small, Chief Information Officer, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. GLWA-CS-071 Change Order No. 4, “Staff Augmentation” with Data Consulting Group, Inc., at an increased cost of $667,520.00, for a total cost not to exceed of $4,114,800.00, with an increase of 12 months for a total duration of five years; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

BACKGROUND

It is necessary for GLWA IT to maintain a core group of highly specialized technical resources.  A limited number of contractual staff are currently retained via Data Consulting Group (DCG).  These contracted resources perform critical software and infrastructure activities for several existing initiatives. Activities include performing corrective and preventative maintenance, making functional improvements, resolving end user issues with mission critical networks and servers, essential databases, business applications, desktops, laptops, and mobile devices. In order to decrease costs and provide for more optimal and sustainable IT operations, the IT Group has worked diligently over the term of contract CS-071 to transition contract resources performing more ongoing operational support and maintenance tasks to direct hire positions.

 

An overview of the contractor roles and transitioned positions are as follows:

Original Contract

1/1/2016 - 12/31/2016

DCG Contractor Roles

Number of Hours

Business Analyst

1150

IT Manager

120

Project Manager

1200

Network Engineer

1960

Service Desk Support

2600

Database Developer Analyst

1640

Programmer Analyst

1960

 

Change Order #1

1/1/2017 - 12/31/2017

DCG Contractor RolesNumber of Hours

 

IT Administration

2264

ERP Project Manager

960

Network Engineer

1960

Service Desk Support

1960

Database Developer Analyst

1960

Programmer Analyst

1960

 

 

 

Change Order #2

7/1/2017 - 12/31/2017

DCG Contractor Roles

Number of Hours

ERP Project Manager 

960

 

1/1/2018 - 12/31/2018

DCG Contractor RolesNumber of Hours

 

Ceridian Project Manager

1000

Database Developer Analyst

1960

Programmer Analyst

1960

Staff Augmentation

TBD

 

Change Order #3:

1/1/2019 - 12/31/2019

DCG Contractor Roles

Number of Hours

Database Developer Analyst

1960

Programmer Analyst

1960

Staff Augmentation

TBD

 

 

Change Order #4:

1/1/2020 - 12/31/2020

DCG Contractor Roles

Number of Hours

Database Developer Analyst

1960

Programmer Analyst

1960

Staff Augmentation

TBD

 

JUSTIFICATION

Contract Change Order #4 to GLWA-CS-071 will allow the Great Lakes Water Authority (GLWA) Information Technology (IT) Group to engage and retain qualified technical resources necessary to implement and support various ongoing and future information systems projects. A limited number of contractual staff are currently retained via Data Consulting Group (DCG).  The Information Technology Group will also engage DCG to recruit and screen additional specialized technical resources for staff augmentation as project needs evolve or new projects arise. Change Order #4 adds additional hours for contractual resources that are actively supporting current active projects. This change order is also structured to include tentative hours for any additional specialized technical resources that may be needed for projects. This change order extends the contract timeline from December 31, 2019 to December 31, 2020 and adds $667,520.00 to GLWA-CS-071, bringing the contract total to $4,114,800.00.

 

PROJECT MANAGEMENT STATUS

 

Original Contract Time                                            12 Months

Change Order No.1:                                            12 Months

Change Order No.2:                                            12 Months

Change Order No.3:                                            12 Months

Proposed Change Order No.4:                       12 Months

New Contract Time                                                                  60 Months

 

 

PROJECT ESTIMATE

Original Contract Price                                           $   822,280.00

Change Order No. 1:                                          $   966,560.00

Change Order No. 2:                                          $   990,920.00

Change Order No. 3:                                          $   667,520.00

Change Order No. 4                                           $   667,520.00

New Contract Total                                                                $ 4,114,800.00

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: Operations & Maintenance Budget

 

Cost Centers: Office of the CIO (Centralized Services 883301)

  Information Technology Business Productivity Systems (Centralized    

  Services 883341)

  Information Technology Enterprise Asset Management Systems

  (Centralized Services 883351)

                                                               

Expense Type: Contract Services - Information Technology (617400)

 

Estimated Cost by Year and Related Estimating Variance: See table below

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on November 13, 2019.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

The indicated programmer analyst provides some labor ITS007 - Departmental Administrative Data Systems (DADS) per the shared services agreement. The resource’s time is documented daily and allocated based on actual time worked. This service is within the scope of the existing shared services agreement.