Great Lakes Water Authority Logo
File #: 2019-364    Version: 1 Name:
Type: Resolution Status: Passed
File created: 9/30/2019 In control: Board of Directors
On agenda: 10/31/2019 Final action: 10/31/2019
Title: Contract No. 1901036 Northeast Water Treatment Plant (NEWTP) Replacement of Covers for Process Water Conduits CIP# 112005/ BCE Score: 61.0
Sponsors: Cheryl Porter, Grant Gartrell
Indexes: Water Operations
Attachments: 1. 1901036 Procurement Report, 2. 1901036 Bid Tab, 3. CIP 112005

Title

Contract No. 1901036

Northeast Water Treatment Plant (NEWTP) Replacement of Covers for Process Water Conduits

CIP# 112005/ BCE Score: 61.0

Body                     

Agenda of:                     October 31, 2019

Item No.:                     2019-364

Amount:                       $1,003,000.00

 

 

TO:                                          The Honorable

                                          Board of Directors

                                          Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                                          Chief Executive Officer

                                          Great Lakes Water Authority

 

DATE:                     October 2, 2019

 

RE:                                          Contract No. 1901036

                                          Northeast Water Treatment Plant (NEWTP) Replacement of Covers
                                          for Process Water Conduits

                                          Vendor:  The LaSalle Group, Inc.

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1901036 “Northeast Water Treatment Plant (NEWTP) Replacement of Covers for Process Water Conduits” with The LaSalle Group, Inc., at a cost not to exceed $1,003,000.00 for a duration of  630 Days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

BACKGROUND

The existing steel covers that protect entry openings into the filtered water conduits at the Northeast Water Treatment Plant are significantly deteriorated and do not provide a water-tight closure. The State of Michigan Department of Environment, Great Lakes, and Energy (EGLE) indicated in its sanitary survey review of the facility that these covers require replacement because of their poor condition. In addition, the covers are not structurally sound and present potential safety hazards to employees. As a temporary measure, the areas surrounding the covers have been barricaded and flagged with “caution” tape to warn personnel of the potentially unsafe conditions. Therefore, the purpose of this proposed construction contract is to replace the existing covers with new covers that are structurally sound, safe, and eliminate concerns with respect to protecting water quality and employee safety.

JUSTIFICATION

Installation of new steel covers for filtered water conduit openings will eliminate concern with respect to unsanitary conditions, as well as eliminating potential safety hazards at the facility.

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.              

Funding Source: Water Construction Bond

Cost Center: Water Engineering

Expense Type: Construction (5519-882111.000-616900-112005)

Estimated Cost by Year and Related Estimating Variance:  See table below.

Fiscal Year

FY 2020 Budget                                                            $     160,000.00

FY 2021 Budget                                                                                                                 640,000.00

  Financial Plan Estimate                                                                                    $     800,000.00

Proposed Contract Award                                                                                        1,003,000.00

Negative Estimating Variance                                                               $    (203,000.00)                                                                                                                                                                                                                                                                                   

This negative estimating variance to be funded from capital reserves.

SAVINGS, COST OPTIMIZATION, AND REVENUE ENHANCEMENT IMPACT

This Project is the replacement of hatch covers of the process water conduits at the Northeast Water Treatment Plant.  Cost savings are not determinable at the time of this award.

 

 

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on October 9, 2019. The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.