File #: 2018-1070    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/2/2019 In control: Board of Directors
On agenda: 1/23/2019 Final action: 1/23/2019
Title: Proposed Change Order No. 4 Contract No. DWS-858 Wick Road Pumping Station Improvements (CIP# 132001)
Sponsors: Cheryl Porter
Indexes: Water Operations
Attachments: 1. Overview of Water & Field Services Change Orders
Related files: 2018-1069

Title

Proposed Change Order No. 4

Contract No. DWS-858

Wick Road Pumping Station Improvements
(CIP# 132001)

 

Body

Agenda of:                     January 23, 2019

Item No.:                     2018-1070

Amount:                      Original Contract:                      $12,138,000.00

                     Previous Change Order Nos. 1-3                     $1,561,409.00

                     Proposed Change Order No. 4          $(152,307.76)

                     Total Revised Contract                      $13,547,101.24

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     January 3, 2019

 

RE:                                          Proposed Change Order No. 4

                     Contract No. DWS-858

                     Wick Road Station Improvements

                     Vendor:  Tooles Contracting Group

 

 

MOTION

Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. DWS-858, Change Order No. 4 “Wick Road Station Improvements” with Tooles Contracting Group, with a credit of $(152,307.76) for a total contract value of $13,547,101.24 and an extension of 973 calendar days for a total contract duration of 3,746 calendar days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

 

 

BACKGROUND

Wick Road Station is a finished water booster pumping station that connects the southern transmission area, serviced primarily by the Southwest Water Treatment Plant; with the northeastern transmission area, serviced by water blended from Springwells and Lake Huron Water Treatment Plants. Tooles Contracting Group and DWSD executed contract number DWS-858 to address necessary upgrades to the Wick Road Station. These upgrades included replacing pumps, motors and drives associated with pump numbers L-1, L-2, and L-3/R-3, new variable frequency drive building enclosure, and the addition of a new passive station bypass.

JUSTIFICATION

The construction contract requires the contractor to provide final waivers from subcontractors and suppliers. Final payment is withheld until all final waivers are provided to GLWA. The prime contractor, Tooles Contracting Group, was not able to secure a final waiver from the pumping equipment supplier until late 2018. The construction work at the site was completed within the revised contract time established through the last change order (Change Order No. 3) to this contract. Upon execution of this proposed Change Order No. 4, GLWA will make final payment to the contractor and will close out the contract. This proposed final Change Order No. 4 also credits GLWA for unused provisional and spare parts allowances that were not used. 

PROJECT MANAGEMENT STATUS

Original Contract Duration                                                                                                                                       1,110 Calendar Days

Change Order Nos. 1-3                                                                                                                                       1,663 Calendar Days

Proposed Change Order No. 4                                                                                                                                973 Calendar Days

New Contract Duration                                                                                                                                       3,746 Calendar Days

Contract Start Date                                                                                                                                                                         November 25, 2008

Original Contract Completion                                                                                                                               December 11, 2011

Revised Contract Completion (Change Order 3)                                                                         June 30, 2016

Change Order No. 4 Final Completion                                                                                                            February 28, 2019

 

PROJECT ESTIMATE

Original Contract Price                                                                                                                                                         $12,138,000.00

Change Order Nos. 1-3                                                                                                                                                          $1,561,409.00

Proposed Change Order No. 4                                                                                                                                       $(152,307.76)

New Contract Total                                                                                                                                                                              $13,547,101.24

 

 

 

FINANCIAL PLAN IMPACT

Summary: Sufficient funds are provided in the financial plan for this project.

Funding Source: Water Construction Bond

Cost Center: Water Engineering

Expense Type: Construction (5519-882111.000-616900-132001)

Estimated Cost by Year and Related Estimating Variance:  See table below.

 

Expenses incurred to-date                                                                  $      13,542,281.24         

 

Contract Value through CO# 3                                                               13,699,409.00

Proposed CO# 4                                                                                                             (152,307.76)

Final Contract                                                                                                         13,547,101.24

 

Negative Estimating Variance                                             $            (4,820.00)

 

Budget amendment to fund negative estimating variance from capital reserves.

 

SAVINGS, COST OPTIMIZATION, AND REVENUE ENHANCEMENT IMPACT

This project provides for improved pumping at Wick Road Station and improvements to bypass flows at Wick Road Station and Ypsilanti Station. Cost savings are not determinable at the time of this award.

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on January 9, 2019.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.