Proposed Change Order No. 4
Contract No. DWS-858
Wick Road Pumping Station Improvements
(CIP# 132001)

Body
Agenda of: January 23, 2019
Item No.: 2018-1070
Amount: Original Contract: $12,138,000.00
Previous Change Order Nos. 1-3 $1,561,409.00
Proposed Change Order No. 4 $(152,307.76)
Total Revised Contract $13,547,101.24

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority

DATE: January 3, 2019

RE: Proposed Change Order No. 4
Contract No. DWS-858
Wick Road Station Improvements
Vendor: Tooles Contracting Group


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. DWS-858, Change Order No. 4 "Wick Road Station Improvements" with Tooles Contracting Group, with a credit of $(152,307.76) for a total contract value of $13,547,101.24 and an extension of 973 calendar days for a total contract duration of 3,746 calendar days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.


BACKGROUND
Wick Road Station is a finished water booster pumping station that connects the southern transmission area, serviced primarily by the Southwest Water Treatment Plant; with the northeastern transmission area, serviced by water blended from Springwells and Lake Huron Water Treatment Plants. Tooles Contracting Group and DWSD executed contract number DWS-858 to address necessary upgrades to the Wick Road Station. These upgrades included replacing pumps, motors and drives associated with pump numbers L-1, L-2, and L-3/R-3, new variable frequency drive building enclosure, and the addition of a new passive station bypass.
JUSTIFICATION
The construction contract requires the contractor to provide final waivers from subcontractors an...

Click here for full text