Great Lakes Water Authority Logo
File #: 2018-730    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/30/2018 In control: Board of Directors
On agenda: 5/23/2018 Final action: 5/23/2018
Title: Contract No. CS-060 - Proposed Change Order No. 1 Engineering Services for the Study, Design and Construction Assistance Services of an Upgraded Enclosed Sludge Conveyance System and Lighting Improvements at the Detroit WRRF Vendor: Black and Veatch LTD
Sponsors: Suzanne Coffey (WRRF)
Indexes: Wastewater Operations
Attachments: 1. GLWA CIP 213007

 

Title

Contract No. CS-060 - Proposed Change Order No. 1

Engineering Services for the Study, Design and Construction Assistance Services of an Upgraded Enclosed Sludge Conveyance System and Lighting Improvements at the Detroit WRRF

Vendor:  Black and Veatch LTD

 

Body

Agenda of:                     May 23, 2018

Item No.:                     2018-730

Amount:                       $96,404.00

 

TO:                     The Honorable

                     Board of Directors

                     Great Lakes Water Authority

 

FROM:                     Sue F. McCormick

                     Chief Executive Officer

                     Great Lakes Water Authority

 

DATE:                     May 4, 2018

 

RE:                                          Contract No. CS-060 - Proposed Change Order No. 1                     

                     Engineering Services for the Study, Design and Construction Assistance Services of an Upgraded Enclosed Sludge Conveyance System and Lighting Improvements at the Detroit WRRF

                     Vendor:  Black and Veatch LTD

 

MOTION

Upon recommendation of Suzanne Coffey, Chief Planning Officer, Interim Chief Operating Officer - Wastewater, The Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to grant an increase of 974 days to the completion date of Contract No. CS-060, “Engineering Services for the Study, Design and Construction Assistance Services of an Upgraded Enclosed Sludge Conveyance System and Lighting Improvements at the Detroit WRRF” with Black and Veatch LTD, with an increase of $96,404.00 in cost with an amended amount not to exceed $2,086,404.00; and  authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote. 

 

 

BACKGROUND

The GLWA’s Water Resource Recovery Facility (WRRF) Complex II Incineration Facility is used to dry and combust dewatered sludge. GLWA had a study and design project of sludge cake conveyance improvements in Complex II in its capital improvement program (CIP). When the fire occurred at the WRRF on March 4, 2016 and severely damaged the belt conveyors feeding Incinerator Complex II, GLWA immediately initiated the study and design for improvements to the sludge conveyance system, which was part of the planned CIP.  Black and Veatch LTD had just completed the design of incinerator upgrades through PC-791 at that time and was very familiar with the sludge conveyance system. Given the emergency at hand, it was requested that Black and Veatch LTD perform the study, design and construction assistance services for the north side sludge cake conveyance improvements in Incineration Complex II as a sole source.

JUSTIFICATION

CS060 was procured as an emergency contract to perform work due to the fire at Incineration Complex II that occurred on March 4, 2016.  A definite scope was not able to be established during the development of this contract. As design progressed, additional scope was introduced to reduce potential fire risks associated with conveyor operations, to improve sludge cake feed to incinerators to allow efficient incinerator performance and to maximize reliability of solids processing.  This design contract was combined with two other small design projects in the same vicinity to enhance constructability and minimize the impact to operations and maintenance. GLWA will also achieve better Quality Assurance and Quality Control on the execution of the construction contract through this additional scope.

 

PROJECT MANAGEMENT STATUS

Original Contract End Date                                          10/31/2018

Change Order No. 1                                           Additional 974 days

New Contract End Date                                           6/19/2021

 

PROJECT ESTIMATE

Original Contract Price                                           $ 1,990,000.00

Change Order No. 1                                           $      96,404.00

New Contract Total                                                                $ 2,086,404.00

 

FINANCIAL PLAN IMPACT

Summary: Reallocation of funds from CIP 260100 WRRF Allowance to CIP 213007

                   CS-060 contract to sufficiently fund the proposed change order request.

Funding Source: Sewer Construction Bond

Cost Center: Wastewater Engineering

Expense Type: Consulting Engineering Services (5421-892211.000-617950-213007)

 

                                          

COMMITTEE REVIEW

This item was presented to the Operations and Resources Committee at its meeting on May 9, 2018.  The Operations and Resources Committee unanimously recommended that the GLWA Board adopt the resolution as presented.

SHARED SERVICES IMPACT

This item does not impact the shared services agreement between GLWA and DWSD.