Title
SCP-CS-1721 Change Order 1
Engineering Services for Water Works Park WTP Chlorine Disinfection System Replacement & Improvements
Body
Agenda of: April 25, 2018
Item No.: 2018-690
Amount: $271,404.06
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority
DATE: April 2, 2018
RE: Contract No. SCP-CS-1721 Change Order 1
Engineering Services for Water Works Park WTP Chlorine Disinfection System Replacement & Improvements
Awarded Vendor: CDM Michigan, Inc.
MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. SCP-CS-1721 Change Order 1 "Engineering Services for Water Works Park WTP Chlorine Disinfection System Replacement & Improvements" with CDM Michigan, Inc., at a cost of $271,404.06 for a total cost not to exceed $961,046.42 and a time extension of 715 calendar days for a total contract duration of 1,281 calendar days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
The scope of the project is to provide design and services during construction for the Water Works Park (WWP) Water Treatment Plant (WTP) chlorine disinfection system replacement and improvements under contract SCP-CS-1721 awarded to CDM Michigan Inc. The project involves the replacement of chlorine scales, evaporators, feeders, eductors, piping, scrubber and HVAC systems to provide reliable pre-chlorination to the Northeast and Springwells WTPs, and to provide reliable, pre-, backwash-, and final-chlorination at WWP WTP. The contract for the construction of the "WWP WTP Chlorine Disinfection System Replacement and Improvements," GLWA-CON-208, was awarded to Detroit Contracting, Inc. on December 19, 2017, and established the start work date as...
Click here for full text