File #: 2022-605    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/22/2022 In control: Board of Directors
On agenda: 1/25/2023 Final action: 1/25/2023
Title: Proposed Amendment No. 3 Contract No. 1903601 Yard Piping Engineering Services CIP #216006
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title
Proposed Amendment No. 3
Contract No. 1903601
Yard Piping Engineering Services
CIP #216006

Body
Agenda of: January 25, 2023
Item No.: 2022-605
Amount: Original Contract Amount $1,647,814.74
Amendment No. 1 434,722.00
Amendment No. 2 765,627.00
Proposed Amendment No. 3 0.00
Total Revised Contract $2,848,163.74

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: December 22, 2022

RE: Proposed Amendment No. 3
Contract No.: 1903601
Yard Piping Engineering Services
Vendor: CDM Smith Michigan, Inc.


MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1903601, Proposed Amendment No. 3, "Yard Piping Engineering Services" with CDM Smith Michigan, Inc., for no increase in cost, for a total cost not to extend $2,848,163.74 and an increased duration of 215 days for a total contract duration of 1,007 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND

GLWA awarded Contract No.1903601 "Yard Piping Engineering Services" to CDM Smith Michigan, Inc. (Engineer), with a start work date of December 28, 2020. The contract is mainly divided into four major phases (study, preliminary design, final design, and construction), with the final design completion date set in the Notice to Proceed as February 27, 2023.
On July 27, 2022, the GLWA Board of Directors authorized Amendment No. 1 for the preliminary and final design phases for the eight recommended improvements. On September 28, 2022, the GLWA Board of Directors Authorized Amendment No. 2 for the preliminary and final design phases for an additional 14 recommended improvements.

...

Click here for full text