Great Lakes Water Authority Logo
File #: 2022-169    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/27/2022 In control: Board of Directors
On agenda: 5/25/2022 Final action: 5/25/2022
Title: Proposed Change Order No. 5 Contract No. GLWA-CON-234 Conner Creek CSO Basin Emergency Rehabilitation Vendor: Weiss Construction Co., LLC
Sponsors: Navid Mehram
Indexes: Wastewater Operations
Attachments: 1. Board Memo_GLWA CON 234 Conner Creek Basin Emergency Rehab

Title
Proposed Change Order No. 5
Contract No. GLWA-CON-234
Conner Creek CSO Basin Emergency Rehabilitation
Vendor: Weiss Construction Co., LLC

Body
Agenda of: May 25, 2022
Item No.: 2022-169
Amount: Original Contract $ 5,058,000.00
Change Order No.1 938,662.00
Change Order No.2 1,268,212.00
Change Order No.3 0.00
Change Order No.4 0.00
Proposed Change Order No.5 0.00
Total Revised Contract $ 7,264,874.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Interim Chief Executive Officer
Great Lakes Water Authority

DATE: April 29, 2022

RE: Proposed Change Order No. 5
Contract No. GLWA-CON-234
Conner Creek CSO Basin Emergency Rehabilitation
Vendor: Weiss Construction Co., LLC

MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. GLWA-CON-234, Proposed Change Order No. 5, "Conner Creek CSO Basin Emergency Rehabilitation" with Weiss Construction Company LLC., for no increase in cost, for a total cost not to exceed $7,264,874.00 and an increased duration of 90 days for a total contract duration of 1,546 days; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND
GLWA-CON-234 contract was awarded to Weiss Construction Company with a start-to-work date of June 12, 2018, and a final completion date of December 12, 2019. The scope of work included repairing Seats and Seals of all sixteen (16) Effluent Launder Gates (ELG) and five (5) Effluent Relief Gates (ERG).
On April 11, 2019, GLWA authorized Weiss Construction Company to replace Seats and Seals to the remaining eleven (11) ERG gates via Change Order No.1 and extended the substantial and final completion date...

Click here for full text