Title: Proposed Change Order No. 3 Contract No.1903598 Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities CIP #216006
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title
Proposed Change Order No. 3
Contract No.1903598
Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities
CIP #216006

Body
Agenda of: January 25, 2023
Item No.: 2022-604
Amount: Original Contract: $4,863,051.00
Change Order No.1: 685,450.00
Change Order No .2 596,779.00
Proposed Change Order No. 3 0.00
Total Revised Contract $6,145,280.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: December 22, 2022

RE: Proposed Change Order No. 3
Contract No. 1903598
Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities
Vendor: The Christman Company

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1903598, Proposed Change Order No. 3, "Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities" with The Christman Company, for no increase in cost, for a total cost not to exceed $6,145,280.00 and an increased duration of 198 days for a total contract duration of 989 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND

GLWA awarded Contract No. 1903598 (Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities) to The Christman Company (Construction Manager) with a start work date of January 15, 2021. This contract is divided into several phases, including study, preliminary design, final design, and construction phase. The original price for Contract No. 1903598 was $4,863,051.00.
On December 8, 2...