Title
Proposed Change Order No. 1
Contract No. 2302932/(SCN-0000231)
Emergency Incineration Complex II Conveyor System Fire Protection Implementations
I&E
Body
Agenda of: February 26, 2025
Item No.: 2025-038
Amount: Original Contract $1,323,000.00
Proposed Change Order No. 1 0.00
Total Contract Amount $1,323,000.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority
DATE: January 27, 2025
RE: Contract No. 2302932/SCN-0000231
Emergency Incineration Complex II Conveyor System Fire Protection Implementations
Vendor: Commercial Contracting Corporation
Status: Amendment/Change Order
MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2302932(SCN-0000231), Proposed Change Order No. 1, "Emergency Incineration Complex II Conveyor System Fire Protection Implementations" with Commercial Contracting Corporation, with no increase in cost for a total cost not to exceed $1,323,000.00 and an increased duration of 111 days for a duration of 385 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
GLWA awarded Commercial Contracting Corporation (CCC) the Construction Contract for the Emergency Incineration C-II Conveyor System Fire Protection Improvements Contract No. 230932. The purpose of the Contract is to provide construction services for the pilot phase of fire protection improvements at the Incineration Complex II Facility of the Water Resource Recovery Facility (WRRF).
This includes installing, integrating, and testing various fire detection technologies and constructing a spray nozzle testing skid. The pilot phase will trigger alarm lights rather than fire-preventing mist...