File #: 2022-271    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/28/2022 In control: Board of Directors
On agenda: 7/27/2022 Final action: 7/27/2022
Title: Proposed Change Order No. 2 Contract No. 1903598 Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities Vendor: The Christman Company
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title
Proposed Change Order No. 2
Contract No. 1903598
Construction Manager at Risk for the Assessment and Rehabilitation of WRRF
Yard Piping and Underground Utilities
Vendor: The Christman Company

Body
Agenda of: July 27, 2022
Item No.: 2022-271
Amount: Original Contract $4,863,051.00
Change Order No.1 685,450.00
Proposed Change Order No. 2 596,779.00
Total Revised Contract $6,145,280.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: July 1, 2022

RE: Proposed Change Order No. 2
Contract No. 1903598
Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities
Vendor: The Christman Company

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1903598, Proposed Change Order No. 2, "Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities" with The Christman Company, at an increased cost of $596,779.00 for a total cost not to exceed $6,145,280.00 with no increase in duration for a total contract duration of 792 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND

GLWA awarded Contract No. 1903598 (Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities) to The Christman Company (Construction Manager) with a start work date of January 15, 2021. This Contract is divided into several phases: study, preliminary design, final design, and construction phase.
Contract No. 1903601 (Yard Piping Engineering services) is a companion contract that GLWA awarded to the Engineer/Consultant ...