Great Lakes Water Authority Logo
File #: 2022-136    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/1/2022 In control: Board of Directors
On agenda: 4/27/2022 Final action: 4/27/2022
Title: Contract No. 2102824 Rehabilitation of Northwest Interceptor - 8 Mile Road to Tireman CIP #260205 / BCE Score: 60.30
Sponsors: Cheryl Porter, Todd King
Indexes: Water Operations
Attachments: 1. 2102824 Procurement Board Report, 2. 2102824 Cost Tabulation - Notice of Respondents
Title
Contract No. 2102824
Rehabilitation of Northwest Interceptor - 8 Mile Road to Tireman
CIP #260205 / BCE Score: 60.30
Body
Agenda of: April 27, 2022
Item No.: 2022-136
Amount: $6,934,703.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Interim Chief Executive Officer
Great Lakes Water Authority

DATE: April 1, 2022

RE: Contract No. 2102824
Rehabilitation of Northwest Interceptor - 8 Mile Road to Tireman
Vendor: LGC Global, Inc.


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. 2102824 "Rehabilitation of Northwest Interceptor - 8 Mile Road to Tireman" with LGC Global, Inc., at a cost not to exceed $6,934,703.00 for a duration of 630 days; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
The GLWA Conveyance System consists of a network of sewers which collect and transfer wastewater to the major interceptors for flow management to the Water Resource Recovery Facility (WRRF). There are three major interceptors - Detroit River Interceptor (DRI), Northwest Interceptor (NWI), and North Interceptor East Arm (NIEA). The Northwest Interceptor (NWI) ranges in diameter from 4 feet to 13 feet.
A condition assessment of about 7.5 miles of this 15 miles long interceptor revealed two severe structural defects in it which were addressed as emergency repairs, both completed under CON-149 (Emergency Sewer Repairs Contract), to avoid a collapse.
GLWA's consultant, FK Engineering, under existing contract CS-168, completed a further assessment of the NWI from 8 Mile to Tireman and designed repairs for rehabilitation of the NWI from 8 Mile to Tireman. Contract No. 2102824 is for this rehabilitation
JUSTIFICATION
Pipeline Assessment and Cer...

Click here for full text