File #: 2022-134    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/1/2022 In control: Board of Directors
On agenda: 4/27/2022 Final action: 4/27/2022
Title: Proposed Change Order No. 4 Contract No. 1802775 Park-Merriman Road 24-Inch Water Main CIP #122011 / BCE Score: 30.2
Sponsors: Cheryl Porter
Indexes: Water Operations
Title
Proposed Change Order No. 4
Contract No. 1802775
Park-Merriman Road 24-Inch Water Main
CIP #122011 / BCE Score: 30.2

Body
Agenda of: April 27, 2022
Item No.: 2022-134
Amount: Original Contract $6,796,714.65
Change Order No. 1 2,093,850.86
Change Order No. 2 273,814.41
Change Order No. 3 0.00
Proposed Change Order No. 4 200,000.00
Total Revised Contract $9,364,379.92

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Interim Chief Executive Officer
Great Lakes Water Authority

DATE: April 1, 2022

RE: Proposed Change Order No. 4
Contract No. 1802775
Park-Merriman Road 24-Inch Water Main
Vendor: Salenbien Trucking & Excavating, Inc.


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. 1802775 Proposed Change Order No. 4 "Park-Merriman Road 24-Inch Water Main" with Salenbien Trucking & Excavating, Inc., at an increased cost of $200,000.00 for a total cost not to exceed $9,364,379.92 and an increased duration of 273 days for a total contract duration of 1,389 days; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
GLWA Contract No. 1802775, Park-Merriman Road 24-inch Water Main, involves the construction of 7,000 linear feet of 24-inch diameter water transmission main. Once completed, this new transmission main will parallel existing single feed main and as a result will provide the necessary redundancy. The Contract was awarded to Salenbien Trucking & Excavating, Inc. (Salenbien) and commenced to run on March 11, 2019. The substantial completion date was June 30, 2021, and the Contract final completion date is April 1, 2022. To date, approximately 6,990 linear feet of 24-inch tr...