Great Lakes Water Authority Logo
File #: 2018-730    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/30/2018 In control: Board of Directors
On agenda: 5/23/2018 Final action: 5/23/2018
Title: Contract No. CS-060 - Proposed Change Order No. 1 Engineering Services for the Study, Design and Construction Assistance Services of an Upgraded Enclosed Sludge Conveyance System and Lighting Improvements at the Detroit WRRF Vendor: Black and Veatch LTD
Sponsors: Suzanne Coffey (WRRF)
Indexes: Wastewater Operations
Attachments: 1. GLWA CIP 213007

Title
Contract No. CS-060 - Proposed Change Order No. 1
Engineering Services for the Study, Design and Construction Assistance Services of an Upgraded Enclosed Sludge Conveyance System and Lighting Improvements at the Detroit WRRF
Vendor: Black and Veatch LTD

Body
Agenda of: May 23, 2018
Item No.: 2018-730
Amount: $96,404.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority

DATE: May 4, 2018

RE: Contract No. CS-060 - Proposed Change Order No. 1
Engineering Services for the Study, Design and Construction Assistance Services of an Upgraded Enclosed Sludge Conveyance System and Lighting Improvements at the Detroit WRRF
Vendor: Black and Veatch LTD

MOTION
Upon recommendation of Suzanne Coffey, Chief Planning Officer, Interim Chief Operating Officer - Wastewater, The Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to grant an increase of 974 days to the completion date of Contract No. CS-060, "Engineering Services for the Study, Design and Construction Assistance Services of an Upgraded Enclosed Sludge Conveyance System and Lighting Improvements at the Detroit WRRF" with Black and Veatch LTD, with an increase of $96,404.00 in cost with an amended amount not to exceed $2,086,404.00; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.


BACKGROUND
The GLWA's Water Resource Recovery Facility (WRRF) Complex II Incineration Facility is used to dry and combust dewatered sludge. GLWA had a study and design project of sludge cake conveyance improvements in Complex II in its capital improvement program (CIP). When the fire occurred at the WRRF on March 4, 2016 and severely damaged the belt conveyors feeding Incinerator Complex II, GLWA immediately initiated the study and design for improvements to the sludge conveyance system, which was part of ...

Click here for full text