Legislation Details

File #: 2026-302    Version: 1 Name:
Type: Resolution Status: New Business
File created: 7/29/2026 In control: Operations and Resources Committee
On agenda: 8/12/2026 Final action:
Title: Requisition No. REQ-0007888 Installation of New 24-inch Water Transmission Main on Merriman Road CIP #122007/BCE Score: 76.8
Sponsors: Cheryl Porter
Indexes: Water Operations
Attachments: 1. REQ-0007888 - Procurement Board Report, 2. REQ-0007888 - Cost Tabulation - Notice of Respondents
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
Requisition No. REQ-0007888
Installation of New 24-inch Water Transmission Main on Merriman Road
CIP #122007/BCE Score: 76.8

Body
Agenda of: August 26, 2026
Item No.: 2026-302
Amount: $3,378,240.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: July 31, 2026

RE: Requisition No. REQ-0007888
Installation of New 24-inch Water Transmission Main on Merriman Road
Vendor: LGC Global, Inc.
Status: New Contract/PO


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Requisition No. REQ-0007888, "Installation of New 24-inch Water Transmission Main on Merriman Road" with LGC Global, Inc., at a cost not to exceed $3,378,240.00 for a duration of 637 days, and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND
This proposed contract is to construct one-half mile of a new 24-inch water main to be installed on Merriman Road between Marquette Street and Cherry Hill Street in Garden City, Michigan, Wayne County. The new 24-inch transmission main will tie into GLWA's existing 42-inch PCCP at Marquette Street and GLWA's existing 16-inch cast iron at Cherry Hill Road. The project includes two tie-ins, installation of gate, triple offset metal-seated ball, and butterfly valves. Installation of this new water main will provide redundancy between our Ford Road Booster Pump Station and Michigan Avenue Booster Pump Station. This is phase I of II for this Capital Improvement Project.
JUSTIFICATION
Recommendation is being requested for this construction contract of a new 24-inch water main on Merriman Road between Marquette Street and Cherry Hill Street in the city of Garden City, Michigan. GLWA's Michigan Avenue Bo...