File #: 2024-317    Version: 1 Name:
Type: Resolution Status: New Business
File created: 9/26/2024 In control: Operations and Resources Committee
On agenda: 10/9/2024 Final action:
Title: Proposed Change Order No. 3 Contract No. 2102824/SCN-0000059 Rehabilitation of the Northwest Interceptor - 8 Mile Road to Tireman CIP #260205/BCE Score: 60.3
Sponsors: Navid Mehram
Indexes: Water Operations
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.


Title
Proposed Change Order No. 3
Contract No. 2102824/SCN-0000059
Rehabilitation of the Northwest Interceptor - 8 Mile Road to Tireman
CIP #260205/BCE Score: 60.3

Body
Agenda of: October 23, 2024
Item No.: 2024-317
Amount: Original Contract Price $6,934,703.00
Change Order No. 1 0.00
Change Order No. 2 938,152.35
Proposed Change Order No. 3 0.00
New Contract Total $7,872,855.35

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: September 26, 2024

RE: Proposed Change Order No. 3
Contract No. 2102824/SCN-0000059
Rehabilitation of the Northwest Interceptor - 8 Mile Road to Tireman
Vendor: LGC Global, Inc.

MOTION
Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2102824/SCN-0000059, Proposed Change Order No. 3, "Rehabilitation of the Northwest Interceptor - 8 Mile Road to Tireman" with LGC Global, Inc., with no increase in cost for a total cost not to exceed $7,872,855.35 and an increased duration of 366 days for a total duration of 1,189 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
The Northwest Interceptor conveyance system generally consists of pipes ranging in diameter from 4 feet to 13 feet and composed of numerous materials, including pre-cast concrete cylinders, cast-in-place concrete, brick, stone, and more. Conveyance projects typically have a few common elements among them, including cleaning and structural or maintenance type repairs followed by warranty inspections 1-year after the defects are repaired to ensure the repairs held. Minor pipe cleaning will occur through September 2024, and then the 1-year warranty inspection clock b...