File #: 2021-477    Version: 1 Name:
Type: Resolution Status: Passed
File created: 12/1/2021 In control: Board of Directors Workshop Meeting
On agenda: 12/8/2021 Final action: 12/8/2021
Title: Proposed Change Order No. 1 Contract No. 1903598 Construction Manager at Risk for the Assessment and Rehabilitation of Water Resource Recovery Facility (WRRF) Yard Piping and Underground Utilities CIP #216006
Sponsors: Navid Mehram
Indexes: Wastewater Operations

Title
Proposed Change Order No. 1
Contract No. 1903598
Construction Manager at Risk for the Assessment and Rehabilitation of Water Resource Recovery Facility (WRRF) Yard Piping and Underground Utilities
CIP #216006

Body
Agenda of: December 8, 2021
Item No.: 2021-477
Amount: Original Contract $4,863,051.00
Proposed Change Order No.1 685,450.00
Total Revised Contract $5,548,501.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Interim Chief Executive Officer
Great Lakes Water Authority

DATE: December 1, 2021

RE: Proposed Change Order No. 1
Contract No. 1903598
Construction Manager at Risk for the Assessment and Rehabilitation of Water Resource Recovery Facility (WRRF) Yard Piping and Underground Utilities
Vendor: The Christman Company

MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. 1903598, Proposed Change Order No. 1 "Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities" with The Christman Company, at an increased cost of $685,450.00 for a total cost not to exceed $5,548,501.00, with no increase in duration; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote.


BACKGROUND

GLWA awarded Contract No.1903598 (Construction Manager at Risk for the Assessment and Rehabilitation of WRRF Yard Piping and Underground Utilities) to The Christman Company with a start work date of January 15, 2021. This Contract is divided into several phases and currently, the contract is in the study/investigation phase. The study phase is expected to be completed by January 2022 and the design phase is expected to be completed by March 2023. The Contract price for Contract No...