File #: 2022-093    Version: 1 Name:
Type: Resolution Status: Passed
File created: 2/28/2022 In control: Board of Directors
On agenda: 3/23/2022 Final action: 3/23/2022
Title: Proposed Amendment No. 1 Contract No. 2002655 Study and Design for Northwest Interceptor Relief Sewer to Oakwood CSO Facility CIP #222001 / BCE Score: 53.6
Sponsors: Cheryl Porter, Todd King
Indexes: Water Operations
Title
Proposed Amendment No. 1
Contract No. 2002655
Study and Design for Northwest Interceptor Relief Sewer to Oakwood CSO Facility
CIP #222001 / BCE Score: 53.6

Body
Agenda of: March 23, 2022
Item No.: 2022-093
Amount: Original Contract Price $5,599,456.00
Proposed Amendment No. 1 96,480.00
New Contract Total $5,695,936.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Interim Chief Executive Officer
Great Lakes Water Authority

DATE: March 2, 2022

RE: Proposed Amendment No. 1
Contract No. 2002655
Study and Design Services for Northwest Interceptor Relief Sewer to Oakwood CSO Facility
Vendor: FK Engineering Associates


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract No. 2002655 Proposed Amendment No. 1 "Study and Design Services for Northwest Interceptor Relief Sewer to Oakwood CSO Facility" with FK Engineering Associates, at an increased cost of $96,480.00 for a total cost not to exceed $5,695,936.00, with no increase in time for a total duration of 1,886 days; and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote.


BACKGROUND
The Northwest Interceptor/Oakwood District Relief Sewer Connector Project was developed as part of the Wastewater Master Plan (WWMP) to maximize the use of existing facilities to treat the wet weather flows. The Oakwood CSO Retention Basin is underutilized, and this project will study, design, and oversee construction of a tunnel to send excess wet weather flows from the Northwest Interceptor (NWI) to the Oakwood basin.
Independent of this project, it has been determined that the influent valves to the Oakwood CSO Basin are non-functional and need to be replaced. Since the influent valves are belo...