File #: 2023-409    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/27/2023 In control: Board of Directors
On agenda: 11/16/2023 Final action: 11/16/2023
Title: Contract No. 2300394 Replacing and Rehabbing Select Roofs at the WRRF CIP #260802 / BCE Score: 77.9
Sponsors: Navid Mehram, Christopher Nastally
Indexes: Wastewater Operations
Attachments: 1. 2300394.ProcurementBoardReport, 2. 2300394.CostTabulation, 3. 2300394.VendorResponseFollow-up

Title
Contract No. 2300394
Replacing and Rehabbing Select Roofs at the WRRF
CIP #260802 / BCE Score: 77.9

Body
Agenda of: November 16, 2023
Item No.: 2023-409
Amount: $3,957,500.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority

DATE: October 27, 2023

RE: Contract No. 2300394
Replacing and Rehabbing Select Roofs at the WRRF
Vendor: Schreiber Corporation


MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 2300394, "Replacing and Rehabbing Select Roofs at the WRRF" with Schreiber Corporation, at a cost not to exceed $3,957,500.00 for a duration of 760 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.


BACKGROUND
GLWA recently completed a study to assess 50 existing building roofs (189 buildings total) that were reported to be in the worst condition on the 130-acre Water Resource Recovery Facility (WRRF) site. Each inspection generated a report and assessment of the overall condition of the roof and then prioritized against each other with the worst roofs reflecting the greatest operational risk due to failure being prioritized ahead of others. A design was then completed for the first package of four roofs to be addressed under this roof improvements program (260800). Other design packages were developed and will be bid out in subsequent years in accordance with the GLWA CIP Program for the WRRF Roof Improvements.
JUSTIFICATION
This project rehabilitates multiple roofs, providing protection from the elements for critical process equipment inside of the facilities. The buildings include the Scum Concentrator Building, Central Offload Facility, Dewatering Complex I, an...