Title
Contract No. GLWA-CS-272
Capital Improvement Program Delivery
Body
Agenda of: February 27, 2019, April 24, 2019, May 8, 2019
Item No.: 2019-191
Amount: $54,934,034.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority
DATE: May 6, 2019
RE: Contract No. GLWA-CS-272
Capital Improvement Program Delivery
Vendor: AECOM Great Lakes, Inc.
MOTION
Upon recommendation of Suzanne Coffey, Chief Planning Officer, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. GLWA-CS-272, "Capital Improvement Program Delivery" with AECOM Great Lakes, Inc., at a cost not to exceed Fifty-Four Million, Nine hundred Thirty-Four Thousand, Thirty-Four Dollars ($54,934,034.00) for a duration of four (4) years, provided that during the term of GLWA CS-272 GLWA staff shall provide to the Board, or a subcommittee of the Board, on at least a quarterly basis, updates on the performance of the Contract including but not limited to the status and progress towards completion of each task identified in the Contract; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
Since its inception, GLWA has significantly retooled its organizational structure and reworked job requirements for many of the positions that are involved in the delivery of the Capital Improvement Plan (CIP). Using its current business processes and staffing, GLWA has achieved the following, combined (Water and Wastewater) annual CIP cash flow results:
? 2016: $36.7 million (initial six-month fiscal year)
? 2017: $97.0 million
? 2018: $107.6 million
? 2019: $75.1 million (as of 12/31/18; six months into fiscal year)
The current 5-year CIP projects a peak delivery of $34...
Click here for full text