Title
Proposed Amendment No. 2
Contract No. 1900455-2/SCN-0000287
Architectural, Engineering, and Design Services
CIP #112007/BCE: 95.2
Body
Agenda of: February 25, 2026
Item No.: 2026-030
Amount: Original Contract $400,000.00
Amendment No. 1 504,040.00
Proposed Amendment No. 2 0.00
Total Contract Amount $904,040.00
TO: The Honorable
Board of Directors
Great Lakes Water Authority
FROM: Suzanne R. Coffey, P.E.
Chief Executive Officer
Great Lakes Water Authority
DATE: January 30, 2026
RE: Proposed Amendment No. 2
Contract No. 1900455-2/SCN-0000287
Architectural, Engineering, and Design Services
Vendor: WSP Michigan, Inc.
Status: Amendment/Change Order
MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. 1900455-2/SCN-0000287, Proposed Amendment No. 2, "Architectural, Engineering, and Design Services" with WSP Michigan, Inc., with no increase in cost at a total cost not to exceed $904,040.00 and an increased duration of 730 days for a total duration of 2,666 days; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
GLWA has multiple facilities that require architectural, engineering design services, including but not limited to: GLWA office facilities, the five (5) water treatment plants, treated water booster pumping stations, wastewater pumping stations, wastewater CSOs, and water resource recovery facilities. The services contract is to provide architectural and engineering design and documentation assistance for planned improvements and/or repairs to GLWA Facilities. The documentation produced is used for planning, soliciting bids, estimating and construction services.
WSP Michigan, Inc., Contract No. 1900455-2 has been working with GLWA Facilities and the Northea...
Click here for full text