Great Lakes Water Authority Logo
File #: 2018-944    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/2/2018 In control: Board of Directors
On agenda: 10/24/2018 Final action: 10/24/2018
Title: GLWA-CON-297 Fairview Sewage Pumping Station Improvements
Sponsors: Cheryl Porter
Indexes: Water Operations
Attachments: 1. GLWA-CON-297 Procurement Report, 2. GLWA-CON-297 Bid Tab
Title
GLWA-CON-297
Fairview Sewage Pumping Station Improvements

Body
Agenda of: October 24, 2018
Item No.: 2018-944
Amount: $28,891,000.00


TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Sue F. McCormick
Chief Executive Officer
Great Lakes Water Authority

DATE: October 2, 2018


RE: Contract No. GLWA-CON-297
Fairview Sewage Pumping Station Improvements
Vendor: Weiss Construction Co., LLC


MOTION
Upon recommendation of Cheryl Porter, Chief Operating Officer - Water and Field Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Chief Executive Officer (CEO) to enter into Contract No. GLWA-CON-297 "Fairview Sewage Pumping Station Improvements" with Weiss Construction Co., LLC, at a cost not to exceed $28,891,000.00 for a duration of two (2) years and seven (7) months; and authorizes the CEO to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND
The Fairview Sewage Pumping Station (Fairview Station) was constructed in 1913 for the purpose of protecting the Water Works Park Water Treatment Plant source water intake from upstream sanitary and combined sewer overflows in the Fox Creek, East Jefferson, Northeast Wayne County, and Southeast Macomb County sewer districts. Currently, the Fairview Station provides the only means for conveying sanitary and combined sewage flows from these sewer districts to the GLWA Water Resource Recovery Facility. All major equipment at the Fairview Station are well beyond their useful service life, are difficult to maintain, and as a result, the station is increasingly vulnerable to operational upsets and unplanned outages. This construction contract, GLWA Contract No. CON-297, will replace the major station mechanical, electrical, instrumentation, and control equipment with new to restore and improve the station's operability, reliability and maintainability.
JUSTIFICATION
The Fairview Sewage Pumping Station lifts...