Great Lakes Water Authority Logo
File #: 2022-007    Version: 1 Name:
Type: Resolution Status: Passed
File created: 1/4/2022 In control: Board of Directors
On agenda: 1/26/2022 Final action: 1/26/2022
Title: Proposed Change Order No. 3 Contract No. GLWA-1802410 Rehabilitation of Various Sampling Sites & PS2 Ferric Chloride System CIP #216004 Vendor: Commercial Contracting Corporation
Sponsors: Navid Mehram
Indexes: Wastewater Operations


Title
Proposed Change Order No. 3
Contract No. GLWA-1802410
Rehabilitation of Various Sampling Sites & PS2 Ferric Chloride System
CIP #216004
Vendor: Commercial Contracting Corporation

Body
Agenda of: January 26, 2022
Item No.: 2022-007
Amount: Original Contract $4,756,000.00
Change Order No.1 806,137.00
Change Order No.2 776,165.00
Proposed Change Order No. 3 217,920.00
Total Revised Contract $6,556,222.00

TO: The Honorable
Board of Directors
Great Lakes Water Authority

FROM: Suzanne R. Coffey P.E.
Interim Chief Executive Officer
Great Lakes Water Authority

DATE: January 4, 2022

RE: Proposed Change Order No. 3
Contract No. GLWA-1802410
Rehabilitation of Various Sampling Sites & PS2 Ferric Chloride System
CIP #216004
Vendor: Commercial Contracting Corporation



MOTION

Upon recommendation of Navid Mehram, Chief Operating Officer - Wastewater Operating Services, the Board of Directors (Board) of the Great Lakes Water Authority (GLWA), authorizes the Interim Chief Executive Officer (ICEO) to enter into Contract GLWA-1802410, Proposed Change Order No. 3, "Rehabilitation of Various Sampling Sites & PS2 Ferric Chloride System", with Commercial Contracting Corporation, at an increased cost of $217,920.00 for a total cost not to exceed $6,556,222.00 and an increased duration of 365 days for a total duration of 1,451 days and authorizes the ICEO to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND

On February 18, 2019, Great Lakes Water Authority awarded the Contract GLWA-1802410 (Rehabilitation of Various Sampling Sites & Pump Station No. 2 Ferric Chloride System), to Commercial Contracting Corporation (CCC). This Contract is comprised of two packages A and B. Package A included the rehabilitation of various sampling sites contained within the GLWA Water Resource Recovery Facility (WRRF). Package B included the replacement of existing...

Click here for full text